Countdown timeline set to complete capital region Ring Road 4 project on schedule

4:24 PM, Wed December 31, 2025

So far, site clearance for the Ring Road 4 project in Hanoi, Bac Ninh and Hung Yen has largely been completed, with about 1,425.82 out of 1,426 hectares cleared, reaching 99.99%.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 1.

Overview of the conference.

On December 31, Politburo member and Hanoi Party Secretary Nguyen Duy Ngoc, Head of the Steering Committee for the Ring Road 4 - Capital Region project, chaired a conference reviewing the project's implementation progress.

The conference was co-chaired by Party Central Committee members Nguyen Huu Nghia, Secretary of the Hung Yen Provincial Party Committee, and Nguyen Hong Thai, Secretary of the Bac Ninh Provincial Party Committee.

Participants also included Party Central Committee member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang, Deputy Minister of Finance Nguyen Duc Tam, Deputy Minister of Construction Le Anh Tuan, Hanoi Vice Party Secretary Nguyen Trong Dong, members of the Steering Committee, and leaders of central ministries, government agencies, Hanoi, Bac Ninh and Hung Yen.

So far, site clearance for the Ring Road 4 project in Hanoi, Bac Ninh and Hung Yen has largely been completed, with about 1,425.82 out of 1,426 hectares cleared, reaching 99.99%.

Authorities have completed grave relocation, resettlement area construction, high-voltage power line relocation and the relocation of underground and aboveground infrastructure.

The Ring Road 4 section in Hanoi spans about 59.2 kilometers, passing through 17 wards and communes. The project required the recovery of 800.15 hectares of land and the relocation of 9,039 graves.

After three years and two months of implementation, ward- and commune-level authorities have completed all 13 resettlement areas. They have finished land acquisition, site clearance, grave relocation and infrastructure relocation on schedule.

The project management board has also completed the relocation of 110kV, 220kV and 500kV power lines in line with construction progress.

The Ring Road 4 section in Hung Yen Province runs about 19.3 kilometers across six communes.

To date, the province has recovered and handed over about 225.66 out of 225.84 hectares to investors, reaching 99.92%. The remaining 1,854 square meters involve five households.

Local authorities have continued to persuade these households to dismantle structures voluntarily, aiming to complete the work before the end of December 31, 2025.

Hung Yen has completed 100% of grave relocation, involving 4,207 graves. The province has also finished relocating all power systems and technical infrastructure and completed the construction of all 11 resettlement areas and seven cemeteries.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 2.

Bac Ninh Party Secretary Nguyen Hong Thai speaks at the conference.

The Ring Road 4 section in Bac Ninh Province extends about 30.6 kilometers and passes through 11 wards and communes.

After more than two years and eight months of implementation, Bac Ninh has completed compensation, support and resettlement for the entire 400 hectares requiring clearance, reaching 100%. The work involved 7,513 households, individuals and organizations.

The province has built eight new resettlement areas and arranged resettlement for 319 households. It has also relocated 2,015 graves. Authorities have largely ensured the relocation of technical infrastructure to support site clearance.

Speaking at the conference, Bac Ninh Party Secretary Nguyen Hong Thai said the province has resolved most site clearance obstacles. However, construction of the parallel road remains slower than required, mainly due to a shortage of more than 600,000 cubic meters of fill material.

After recent reviews and working sessions, Bac Ninh expects to fully resolve this issue before January 10, 2026. The province aims to ensure ground leveling progress and accelerate road construction.

Following the conference, provincial agencies will continue to urge contractors to review all items, concentrate maximum resources and speed up construction to complete the parallel road as early as possible.

Regarding the budget and financial mechanisms, Thai stressed that implementing National Assembly resolutions remains mandatory.

However, he said policymakers must carefully calculate mechanisms and policies to ensure balance and harmony among localities, without creating excessive budget pressure.

He noted that although Bac Ninh has relatively strong budget revenues, the province still faces many difficulties, especially in social welfare and poverty reduction, which require large annual expenditures.

Therefore, if total investment does not exceed the approved ceiling, authorities should carefully consider adjustments to the spending structure.

Thai also urged the Steering Committee and relevant agencies to study, report and propose appropriate balancing solutions among localities that reflect practical conditions.

For the next phase, he called on the Standing Agency of the Steering Committee and relevant localities to urgently develop a unified overall schedule across the three localities.

The plan should ensure synchronized implementation and clearly define milestones using a "countdown" approach toward project completion.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 3.

Hung Yen Party Secretary Nguyen Huu Nghia speaks at the meeting.

Hung Yen Party Secretary Nguyen Huu Nghia said the project's success so far stems from regular attention and direction from central authorities and the Steering Committee.

He also highlighted effective public communication and consensus-building, inter-provincial coordination to resolve shared challenges and close cooperation among departments within each locality.

Concluding the conference, Hanoi Party Secretary Nguyen Duy Ngoc praised agencies and units in Hanoi, Hung Yen and Bac Ninh for completing tasks assigned by the Steering Committee at its November 26, 2025 conclusion meeting.

He said their efforts ensured project progress, especially in site clearance, which has supported construction schedules.

Regarding upcoming tasks, Ngoc directed adjustments to the project's capital allocation for Bac Ninh. The Steering Committee will soon issue formal guidance to support overall project progress.

On adjusting interchanges along the route, he stressed the need for synchronization and optimized traffic connectivity to accelerate construction.

On architecture and landscape design, he urged Hung Yen and Bac Ninh to coordinate closely with Hanoi to ensure unified, durable architecture and promote modern, sustainable urban development along Ring Road 4.

Ngoc also called on localities and relevant units to take advantage of favorable weather conditions to speed up construction, ensuring progress on the parallel roads and the entire project.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 4.

Hanoi Party Secretary Nguyen Duy Ngoc speaks at the meeting.

Regarding construction materials, he directed agencies to study alternative materials in line with the Ministry of Construction regulations.

Emphasizing that the Steering Committee will soon propose solutions, Ngoc asked the Ministry of Construction to coordinate with localities to develop specific plans to address material shortages across the project.

"The Standing Agency of the Steering Committee will direct the standing agencies of the three localities to prepare a unified construction plan for the entire Ring Road 4 route, register a countdown timeline for project completion with the Government and relevant ministries and ensure consistent implementation," Ngoc said.

Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region

15:18 21/05/2026

On May 21, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha inspected the construction site and worked with departments, agencies and related units on the implementation progress of the second campus project of Hanoi Heart Hospital in Xuan Dinh Ward.

Most views
Same category
Find by date
Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region
Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region
On May 21, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha inspected the construction site and worked with departments, agencies and related units on the implementation progress of the second campus project of Hanoi Heart Hospital in Xuan Dinh Ward.
15:18 21/05/2026
Hanoi strengthens strategic partnership with Saint Petersburg through expanding legislative cooperation initiatives
Hanoi strengthens strategic partnership with Saint Petersburg through expanding legislative cooperation initiatives
As part of Hanoi’s 2026 foreign affairs agenda, a Hanoi delegation visited and worked in Saint Petersburg, Russia, from May 18 to May 20 at the invitation of the Legislative Assembly and the External Relations Committee of Saint Petersburg.
15:17 21/05/2026
Hanoi launches smart eco-industrial park advancing northern innovation and manufacturing growth ambitions
Hanoi launches smart eco-industrial park advancing northern innovation and manufacturing growth ambitions
On May 20, the Hanoi People's Committee and the Vietnam Construction and Import-Export Joint Stock Corporation (VINACONEX) broke ground on the Dong Anh Industrial Park infrastructure construction and business investment project.
15:18 20/05/2026
Hanoi launches major waste-to-energy plant advancing sustainable urban environmental transformation goals
Hanoi launches major waste-to-energy plant advancing sustainable urban environmental transformation goals
The Nui Thoong High-Tech Environmental Treatment and Waste-to-Energy Plant project is the first high-tech waste-to-energy plant project in southwestern Hanoi and is expected to become a strategic component in the capital's waste-to-energy development network.
15:10 19/05/2026
Hanoi honors veteran Party members for revolutionary dedication
Hanoi honors veteran Party members for revolutionary dedication
On the occasion of the 136th anniversary of President Ho Chi Minh's birth (May 19, 1890 - May 19, 2026), the Hanoi Party Committee on May 19 organized a ceremony to award 80-year, 75-year and 70-year Party membership badges in the May 19, 2026 recognition round.
15:10 19/05/2026
New highway corridor reshapes southern Hanoi with ambitious urban redevelopment vision
New highway corridor reshapes southern Hanoi with ambitious urban redevelopment vision
The project carries special significance for the city's strategy to develop urban space, strengthen regional connectivity and modernize southern Hanoi's infrastructure system in the new development phase.
15:09 19/05/2026
Other news
Hanoi Chairman calls for waste treatment linked to green urban recovery
Hanoi Chairman calls for waste treatment linked to green urban recovery
Chairman of the Hanoi People's Committee Vu Dai Thang on May 20 inspected the Xuan Son solid waste treatment complex and visited the Seraphin waste-to-energy plant operated by AMACCAO Group, where city officials reviewed the overall status of solid waste treatment across Hanoi.
15:15 20/05/2026
Hanoi urges faster progress on Yen Ky cemetery park project
Hanoi urges faster progress on Yen Ky cemetery park project
A Hanoi delegation led by Vu Dai Thang, member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on May 20 inspected the Vinh Hang Cemetery in Vat Lai Commune and reviewed reports on planning, investment, and management of the Vinh Hang and Yen Ky cemetery projects, along with other cemeteries across the city.
15:14 20/05/2026
Hanoi steps up digital transformation and innovation in culture
Hanoi steps up digital transformation and innovation in culture
The Hanoi People's Committee Office has issued Notice No. 404/TB-VP, dated May 19, 2026, outlining conclusions by Vice Chairman of the Hanoi People's Committee Truong Viet Dung at a meeting reviewing digital transformation, science and technology, and innovation in the cultural sector.
15:16 19/05/2026
Hanoi breaks ground on Phu Ha industrial park, targets green industrial model
Hanoi breaks ground on Phu Ha industrial park, targets green industrial model
Hanoi authorities on the morning of May 19 held the groundbreaking ceremony for the Phu Ha Industrial Park project, covering nearly 175 hectares with a total investment of more than VND2.9 trillion (US$111.5 million). The project will be developed in Chuong Duong and Thuong Phuc communes.
15:14 19/05/2026
Hanoi signs MoU on electric motorcycle battery swap station project
Hanoi signs MoU on electric motorcycle battery swap station project
Truong Viet Dung, Vice Chairman of the Hanoi People's Committee, on the morning of May 19, presided over the signing ceremony for a memorandum of understanding among the Hanoi Department of Construction, LG Energy Solution of South Korea, and Honda Motor of Japan on a project to install battery swap stations for electric motorcycles in Hanoi.
14:29 19/05/2026
Hanoi strengthens child protection and prevention of violence and abuse against children
Hanoi strengthens child protection and prevention of violence and abuse against children
Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha has signed Official Dispatch No. 2133/UBND-KGVX, dated May 18, 2026, on strengthening child protection and the prevention of violence and abuse against children.
15:04 18/05/2026
Hanoi eyes western growth boost through cultural village transfer
Hanoi eyes western growth boost through cultural village transfer
A Hanoi delegation led by Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on May 18, conducted a field inspection and held a working session with the Ministry of Culture, Sports and Tourism and related agencies regarding the transfer and handover of the Vietnam National Village for Ethnic Culture and Tourism.
14:36 18/05/2026
Hanoi moves ahead with plan to take over Ba Vi National Park
Hanoi moves ahead with plan to take over Ba Vi National Park
Vu Dai Thang, member of the Party Central Committee, deputy secretary of the Hanoi Party Committee and chairman of the Hanoi People’s Committee, led a city delegation on May 18 to inspect preparations for Ba Vi National Park’s handover to the city and its subsequent management.
14:28 18/05/2026