Countdown timeline set to complete capital region Ring Road 4 project on schedule

4:24 PM, Wed December 31, 2025

So far, site clearance for the Ring Road 4 project in Hanoi, Bac Ninh and Hung Yen has largely been completed, with about 1,425.82 out of 1,426 hectares cleared, reaching 99.99%.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 1.

Overview of the conference.

On December 31, Politburo member and Hanoi Party Secretary Nguyen Duy Ngoc, Head of the Steering Committee for the Ring Road 4 - Capital Region project, chaired a conference reviewing the project's implementation progress.

The conference was co-chaired by Party Central Committee members Nguyen Huu Nghia, Secretary of the Hung Yen Provincial Party Committee, and Nguyen Hong Thai, Secretary of the Bac Ninh Provincial Party Committee.

Participants also included Party Central Committee member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang, Deputy Minister of Finance Nguyen Duc Tam, Deputy Minister of Construction Le Anh Tuan, Hanoi Vice Party Secretary Nguyen Trong Dong, members of the Steering Committee, and leaders of central ministries, government agencies, Hanoi, Bac Ninh and Hung Yen.

So far, site clearance for the Ring Road 4 project in Hanoi, Bac Ninh and Hung Yen has largely been completed, with about 1,425.82 out of 1,426 hectares cleared, reaching 99.99%.

Authorities have completed grave relocation, resettlement area construction, high-voltage power line relocation and the relocation of underground and aboveground infrastructure.

The Ring Road 4 section in Hanoi spans about 59.2 kilometers, passing through 17 wards and communes. The project required the recovery of 800.15 hectares of land and the relocation of 9,039 graves.

After three years and two months of implementation, ward- and commune-level authorities have completed all 13 resettlement areas. They have finished land acquisition, site clearance, grave relocation and infrastructure relocation on schedule.

The project management board has also completed the relocation of 110kV, 220kV and 500kV power lines in line with construction progress.

The Ring Road 4 section in Hung Yen Province runs about 19.3 kilometers across six communes.

To date, the province has recovered and handed over about 225.66 out of 225.84 hectares to investors, reaching 99.92%. The remaining 1,854 square meters involve five households.

Local authorities have continued to persuade these households to dismantle structures voluntarily, aiming to complete the work before the end of December 31, 2025.

Hung Yen has completed 100% of grave relocation, involving 4,207 graves. The province has also finished relocating all power systems and technical infrastructure and completed the construction of all 11 resettlement areas and seven cemeteries.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 2.

Bac Ninh Party Secretary Nguyen Hong Thai speaks at the conference.

The Ring Road 4 section in Bac Ninh Province extends about 30.6 kilometers and passes through 11 wards and communes.

After more than two years and eight months of implementation, Bac Ninh has completed compensation, support and resettlement for the entire 400 hectares requiring clearance, reaching 100%. The work involved 7,513 households, individuals and organizations.

The province has built eight new resettlement areas and arranged resettlement for 319 households. It has also relocated 2,015 graves. Authorities have largely ensured the relocation of technical infrastructure to support site clearance.

Speaking at the conference, Bac Ninh Party Secretary Nguyen Hong Thai said the province has resolved most site clearance obstacles. However, construction of the parallel road remains slower than required, mainly due to a shortage of more than 600,000 cubic meters of fill material.

After recent reviews and working sessions, Bac Ninh expects to fully resolve this issue before January 10, 2026. The province aims to ensure ground leveling progress and accelerate road construction.

Following the conference, provincial agencies will continue to urge contractors to review all items, concentrate maximum resources and speed up construction to complete the parallel road as early as possible.

Regarding the budget and financial mechanisms, Thai stressed that implementing National Assembly resolutions remains mandatory.

However, he said policymakers must carefully calculate mechanisms and policies to ensure balance and harmony among localities, without creating excessive budget pressure.

He noted that although Bac Ninh has relatively strong budget revenues, the province still faces many difficulties, especially in social welfare and poverty reduction, which require large annual expenditures.

Therefore, if total investment does not exceed the approved ceiling, authorities should carefully consider adjustments to the spending structure.

Thai also urged the Steering Committee and relevant agencies to study, report and propose appropriate balancing solutions among localities that reflect practical conditions.

For the next phase, he called on the Standing Agency of the Steering Committee and relevant localities to urgently develop a unified overall schedule across the three localities.

The plan should ensure synchronized implementation and clearly define milestones using a "countdown" approach toward project completion.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 3.

Hung Yen Party Secretary Nguyen Huu Nghia speaks at the meeting.

Hung Yen Party Secretary Nguyen Huu Nghia said the project's success so far stems from regular attention and direction from central authorities and the Steering Committee.

He also highlighted effective public communication and consensus-building, inter-provincial coordination to resolve shared challenges and close cooperation among departments within each locality.

Concluding the conference, Hanoi Party Secretary Nguyen Duy Ngoc praised agencies and units in Hanoi, Hung Yen and Bac Ninh for completing tasks assigned by the Steering Committee at its November 26, 2025 conclusion meeting.

He said their efforts ensured project progress, especially in site clearance, which has supported construction schedules.

Regarding upcoming tasks, Ngoc directed adjustments to the project's capital allocation for Bac Ninh. The Steering Committee will soon issue formal guidance to support overall project progress.

On adjusting interchanges along the route, he stressed the need for synchronization and optimized traffic connectivity to accelerate construction.

On architecture and landscape design, he urged Hung Yen and Bac Ninh to coordinate closely with Hanoi to ensure unified, durable architecture and promote modern, sustainable urban development along Ring Road 4.

Ngoc also called on localities and relevant units to take advantage of favorable weather conditions to speed up construction, ensuring progress on the parallel roads and the entire project.

Countdown timeline set to complete capital region Ring Road 4 project on schedule- Ảnh 4.

Hanoi Party Secretary Nguyen Duy Ngoc speaks at the meeting.

Regarding construction materials, he directed agencies to study alternative materials in line with the Ministry of Construction regulations.

Emphasizing that the Steering Committee will soon propose solutions, Ngoc asked the Ministry of Construction to coordinate with localities to develop specific plans to address material shortages across the project.

"The Standing Agency of the Steering Committee will direct the standing agencies of the three localities to prepare a unified construction plan for the entire Ring Road 4 route, register a countdown timeline for project completion with the Government and relevant ministries and ensure consistent implementation," Ngoc said.

Hanoi promotes election law awareness for ethnic communities in 5 minority communes

09:44 10/03/2026

The Hanoi Department of Ethnic and Religious Affairs on March 10 organized a conference to disseminate and explain the Law on the Election of Deputies to the National Assembly and People’s Councils for ethnic minority residents in Ba Vi Commune.

Most views
Same category
Find by date
Hanoi promotes election law awareness for ethnic communities in 5 minority communes
Hanoi promotes election law awareness for ethnic communities in 5 minority communes
The Hanoi Department of Ethnic and Religious Affairs on March 10 organized a conference to disseminate and explain the Law on the Election of Deputies to the National Assembly and People’s Councils for ethnic minority residents in Ba Vi Commune.
09:44 10/03/2026
Hanoi promotes friendship toward comprehensive economic partnership between Vietnam and India
Hanoi promotes friendship toward comprehensive economic partnership between Vietnam and India
The Hanoi Union of Friendship Organizations, in coordination with the Institute for South Asian, West Asian and African Studies under the Vietnam Academy of Social Sciences, the Embassy of India in Vietnam, and the Hanoi Vietnam–India Friendship Association, on March 10, held an international conference titled "Promoting Friendship Toward a Comprehensive Economic Partnership Between Vietnam and India."
09:39 10/03/2026
Hanoi vice chairwoman inspects election preparations in Hong Ha Ward ahead of voting day
Hanoi vice chairwoman inspects election preparations in Hong Ha Ward ahead of voting day
On March 3, at the Hong Ha Ward People's Committee, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha chaired an inspection meeting on preparations for the election of deputies to the 16th National Assembly and People's Councils for the 2026–2031 term in the ward.
16:56 03/03/2026
Hanoi leads nationwide in comprehensive preparation for upcoming elections
Hanoi leads nationwide in comprehensive preparation for upcoming elections
At the February review meeting and the launch of tasks for March 2026, Phung Thi Hong Ha, Deputy Secretary of the Hanoi Party Committee and Chairwoman of the Hanoi People's Council, said March and the second quarter of 2026 would be a decisive period for finalizing materials for the fifth conference of the Hanoi Party Committee and preparing for the first session and the mid-year regular session of the city People's Council.
16:51 03/03/2026
Officials must elevate capacity and mindset to meet unprecedented responsibilities ahead
Officials must elevate capacity and mindset to meet unprecedented responsibilities ahead
Concluding the February work review meeting and launching tasks for March 2026, Politburo member and Secretary of the Hanoi Party Committee Nguyen Duy Ngoc said the capital achieved many positive results in February.
16:50 03/03/2026
Hanoi Fatherland Front strengthens oversight to ensure democratic and lawful election process
Hanoi Fatherland Front strengthens oversight to ensure democratic and lawful election process
Speaking at the February work review meeting and outlining key tasks for March 2026, Bui Huyen Mai, member of the Hanoi Party Committee's Standing Board and Chairwoman of the Vietnam Fatherland Front Committee of Hanoi, highlighted four major groups of tasks for the coming month.
16:31 03/03/2026
Other news
Hanoi moves to secure fuel supply, cracks down on hoarding and speculation
Hanoi moves to secure fuel supply, cracks down on hoarding and speculation
Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on the morning of March 10, chaired a meeting to review the operation of fuel trading and fuel supply across the city.
10:05 10/03/2026
Hanoi Mayor urges craft village, industrial cluster growth
Hanoi Mayor urges craft village, industrial cluster growth
Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee, on the morning of March 10 chaired a meeting to hear an overview report on the management and development of craft villages and industrial clusters across the city.
10:05 10/03/2026
Hanoi promotes regulations and policies to attract talented people
Hanoi promotes regulations and policies to attract talented people
Standing Vice Chairman of the Hanoi People's Committee Duong Duc Tuan has signed and issued Plan No. 92/KH-UBND, dated March 9, 2026, on implementing the Resolution of the Hanoi People's Council promulgating regulations on mechanisms and policies to attract and make effective use of talented people in Hanoi.
10:06 09/03/2026
Hanoi approves project on disability inclusion for water governance and climate adaptation
Hanoi approves project on disability inclusion for water governance and climate adaptation
Vice Chairman of the Hanoi People's Committee Nguyen Manh Quyen has signed Decision No. 1001/QD-UBND dated March 9, 2026 approving the project document titled "Promoting the Inclusion of Persons with Disabilities in Water Resource Governance and Climate Change Adaptation in Vietnam."
09:45 09/03/2026
Hanoi implements measures to ensure fuel supply
Hanoi implements measures to ensure fuel supply
Nguyen Manh Quyen, Vice Chairman of the Hanoi People's Committee, has signed and issued Official Letter No. 966/UBND-KT dated March 9, 2026 on implementing measures to ensure fuel supply and limit the impact of fuel price fluctuations on growth targets and socio-economic activities across the city.
09:33 09/03/2026
Hanoi promotes efficiency in implementing and enforcing Law on Drug Prevention and Control
Hanoi promotes efficiency in implementing and enforcing Law on Drug Prevention and Control
Standing Vice Chairman of the Hanoi People's Committee Duong Duc Tuan has signed and issued Plan No. 89/KH-UBND, dated March 7, 2026, on implementing and enforcing the 2025 Law on Drug Prevention and Control across Hanoi.
10:22 07/03/2026
Hanoi strengthens leadership in care and protection of children in special circumstances
Hanoi strengthens leadership in care and protection of children in special circumstances
Vice Chairman of the Hanoi People's Committee Vu Thu Ha has signed and issued Plan No. 88/KH-UBND, dated March 7, 2026, on implementing Directive No. 07-CT/TU dated February 12, 2026, issued by the Standing Committee of the Hanoi Party Committee on strengthening leadership in the care and protection of children in special circumstances across Hanoi.
10:09 07/03/2026
Hanoi accelerates two strategic infrastructure projects to ensure progress, quality and investment efficiency
Hanoi accelerates two strategic infrastructure projects to ensure progress, quality and investment efficiency
Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee, on the morning of March 5 presented a comprehensive report on the implementation of the Ring Road 4 – Capital Region project and the road connecting Gia Binh Airport to Hanoi at the 24th meeting of the State Steering Committee for nationally important transport projects.
10:04 05/03/2026