Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects

5:55 PM, Sun April 19, 2026

Politburo Member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang on the afternoon of April 19 continued his on-site inspections of major infrastructure projects in the capital, including the Me So Bridge-Component Project 3 of the Ring Road 4 – Hanoi Capital Region Investment Project; the Ngoc Hoi Bridge and its approach roads; and the Ring Road 2.5 project.

Bí thư Thành ủy Trần Đức Thắng và Phó Bí thư Thường trực Thành ủy Nguyễn Trọng Đông kiểm tra thực địa tại dự án cầu Mễ Sở.

Hanoi Party Secretary Tran Duc Thang and Standing Deputy Party Secretary Nguyen Trong Dong conducted field inspections at the Me So Bridge project.

Also joining the delegation were Central Committee Member and Standing Deputy Party Secretary Nguyen Trong Dong; Member of the Hanoi Party Standing Committee and Standing Vice Chairman of the Hanoi People's Committee Duong Duc Tuan; along with representatives of relevant departments, agencies, and local authorities.

Regarding the Me So Bridge component under Ring Road 4 – Capital Region, construction is being carried out intensively as part of Component Project 3 under a BOT (build-operate-transfer) model.

Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects- Ảnh 2.Rendering of the Me So Bridge project

On the Hanoi side, site clearance has been fully completed. On the Hung Yen side, one household and four power lines crossing the route remain unresolved, with local authorities working to finalize clearance in April 2026. 

Additional land acquisition areas following design adjustments at several interchanges and connecting branches are also nearing completion, including site clearance and relocation of technical infrastructure.

Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects- Ảnh 3.Hanoi Party Secretary Tran Duc Thang and Standing Deputy Party Secretary Nguyen Trong Dong inspect the Me So Bridge project

To meet the schedule, contractors are maintaining multiple work fronts for substructure and approach bridge construction. To date, 249 out of 596 bored piles have been completed, along with 14 pile caps, two piers, and three SuperT girders. 

The project has reached an output value of approximately VND622 billion (US$24.9 million), equivalent to 19.26% of the contract. The main bridge alone accounts for about VND380 billion (US$15.2 million) out of VND1.8 trillion (US$72 million), exceeding the planned schedule by 4.58%.

The Project Management Board and contractors have developed a construction plan to mitigate impacts during the 2026 rainy and flood season. The target is to complete four K0 segments of the main pylons by December 25, 2026, and close the main span between piers P3–P4 by September 10, 2027.

Cumulative disbursement for Component Project 3 has reached 81.2%, generally meeting schedule requirements. However, pressure from material supply constraints and fluctuations in fuel prices is directly affecting construction progress, requiring close coordination in price disclosure and the assurance of material supply.

For the Ngoc Hoi Bridge and its approach roads, construction began on August 19, 2025. Contractors are now deploying multiple work fronts simultaneously, aiming for completion ahead of the APEC Summit. The main bridge crossing the Red River has completed 72 out of 80 bored piles for the main tower piers, with full completion expected in April 2026.

The approach bridge has completed 802 out of 2,242 bored piles, cast 11 out of 2,220 SuperT girders, and finished 9 out of 160 pile caps. In April 2026, the plan is to increase output to 950 bored piles, 50 SuperT girders, and 30 pile caps. At the same time, casting yard construction and service road works are being maintained continuously.

In terms of land clearance, the Hanoi side has handed over the full 32.6 hectares. Hung Yen has handed over 12.8 out of 22.66 hectares. Remaining obstacles include four pressure relief wells within the Red River right-bank dike corridor and several power, water, and telecommunications facilities that must be relocated alongside land handover.

In 2025, the project disbursed 100% of its allocated capital. In 2026, disbursement has reached 44% of the city's annual plan. Progress depends heavily on completing the remaining land clearance in Van Giang district and resolving technical infrastructure along the route.

For the Ring Road 2.5 section through Cau Giay Ward, spanning 1,130 meters in two segments, efforts are focused on completing land clearance for construction. The 420-meter section from Cau Giay Street to Dich Vong New Urban Area has approved all 338 compensation plans, with 337 handed over, reaching 99.7%. One remaining case involves a historical site undergoing dismantling and relocation.

The 710-meter section from Dich Vong New Urban Area to Duong Dinh Nghe Street has been implemented under an emergency construction order since January 4, 2026. In less than three months, the ward relocated 359 graves, seven days ahead of schedule. To date, 29,701 out of 32,159 square meters have been acquired, reaching 92.4%, with 24,656 square meters handed over to the investor for construction.

The remaining 7.6%, equivalent to 39 cases covering 2,458 square meters, is being handled in accordance with regulations. Construction began on March 20, 2026, allowing parallel implementation of construction and land clearance, with the goal of completing full handover as directed by the city.

Speaking at the site, Hanoi Party Secretary Tran Duc Thang commended project investors, contractors, and local authorities for accelerating progress and meeting planned targets.

He noted that the Me So Bridge is a key driver project connecting Hanoi with neighboring provinces, opening new development space for the southern and southeastern areas of the city, easing pressure on existing routes, and facilitating goods transport and travel. Any delay, he stressed, would directly affect both the capital and the broader capital region, and must be avoided.

Thang instructed the Project Management Board, Hong Van commune, and related units to closely monitor all tasks under Hanoi's responsibility, especially land clearance, construction of service roads, and material stockyards, to ensure uninterrupted construction conditions. Difficulties in coordination with central ministries and Hung Yen province must be fully consolidated, clearly reported, and accompanied by concrete solutions, without being left unresolved at lower levels.

Given that construction takes place over the Red River, he emphasized strict requirements on labor safety, inland waterway and road traffic safety, environmental protection, and river flow management. All procedures and regulations must be strictly followed. Any violations leading to safety incidents will result in strict accountability for contractors, supervisors, and related individuals. The city will closely monitor each milestone, linking leadership responsibility to specific results at every stage.

For the Ngoc Hoi Bridge, Thang highlighted its critical role in enhancing southern connectivity, easing pressure on existing bridges and road networks, and opening up new development space for Thanh Tri Commune and surrounding areas. Completion will directly benefit tens of thousands of households and businesses currently facing congestion and prolonged travel times.

He set clear deadlines: Hung Yen province must complete site clearance for the remaining 12.66 hectares of agricultural land by June 30, 2026, and for residential land by July 15, 2026. Hanoi's Department of Agriculture and Environment must coordinate the clearance of pressure relief wells within the Red River dike corridor by May 10, 2026. Hanoi's Department of Construction must coordinate the dredging of approximately 40,000 cubic meters of sediment to ensure construction progress.

The Project Management Board was instructed to review all remaining obstacles related to land and technical infrastructure, ensuring no case is overlooked, and to resolve all issues within its authority on schedule. Accountability will be clearly assigned to agencies, units, and individuals in cases of delayed procedures due to a lack of coordination or supervision.

Investors and contractors must report clearly on the progress of each component and ensure traffic safety during construction. Progress must go hand in hand with quality. Any changes to the schedule must be clearly explained, with justified reasons and specific corrective measures. Close coordination among all parties is required to ensure progress, with the goal of completing the project in the second quarter of 2027.

At the Ring Road 2.5 project, Hanoi Party Secretary Tran Duc Thang noted that once completed, the route will significantly reduce congestion and improve daily travel, work, and study conditions for residents. Any delay would directly impact people's lives.

He instructed Cau Giay, Yen Hoa, and Thanh Xuan wards, along with the Project Management Board and relevant departments, to review each remaining land clearance issue. Every bottleneck must have a clear solution, a defined deadline, and an assigned responsible party.

Cau Giay Ward must complete land clearance for remaining households no later than May 15, 2026. For other sections, including Vu Pham Ham – Tran Duy Hung and Nguy Nhu Kon Tum – Nguyen Trai, relevant departments and local authorities must urgently resolve outstanding issues to complete land clearance and enable contractors to meet the planned schedule.

Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region

15:18 21/05/2026

On May 21, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha inspected the construction site and worked with departments, agencies and related units on the implementation progress of the second campus project of Hanoi Heart Hospital in Xuan Dinh Ward.

Most views
Same category
Find by date
Hanoi Chairman calls for waste treatment linked to green urban recovery
Hanoi Chairman calls for waste treatment linked to green urban recovery
Chairman of the Hanoi People's Committee Vu Dai Thang on May 20 inspected the Xuan Son solid waste treatment complex and visited the Seraphin waste-to-energy plant operated by AMACCAO Group, where city officials reviewed the overall status of solid waste treatment across Hanoi.
15:15 20/05/2026
Hanoi urges faster progress on Yen Ky cemetery park project
Hanoi urges faster progress on Yen Ky cemetery park project
A Hanoi delegation led by Vu Dai Thang, member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on May 20 inspected the Vinh Hang Cemetery in Vat Lai Commune and reviewed reports on planning, investment, and management of the Vinh Hang and Yen Ky cemetery projects, along with other cemeteries across the city.
15:14 20/05/2026
Hanoi breaks ground on Phu Ha industrial park, targets green industrial model
Hanoi breaks ground on Phu Ha industrial park, targets green industrial model
Hanoi authorities on the morning of May 19 held the groundbreaking ceremony for the Phu Ha Industrial Park project, covering nearly 175 hectares with a total investment of more than VND2.9 trillion (US$111.5 million). The project will be developed in Chuong Duong and Thuong Phuc communes.
15:14 19/05/2026
Hanoi signs MoU on electric motorcycle battery swap station project
Hanoi signs MoU on electric motorcycle battery swap station project
Truong Viet Dung, Vice Chairman of the Hanoi People's Committee, on the morning of May 19, presided over the signing ceremony for a memorandum of understanding among the Hanoi Department of Construction, LG Energy Solution of South Korea, and Honda Motor of Japan on a project to install battery swap stations for electric motorcycles in Hanoi.
14:29 19/05/2026
Hanoi eyes western growth boost through cultural village transfer
Hanoi eyes western growth boost through cultural village transfer
A Hanoi delegation led by Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on May 18, conducted a field inspection and held a working session with the Ministry of Culture, Sports and Tourism and related agencies regarding the transfer and handover of the Vietnam National Village for Ethnic Culture and Tourism.
14:36 18/05/2026
Hanoi moves ahead with plan to take over Ba Vi National Park
Hanoi moves ahead with plan to take over Ba Vi National Park
Vu Dai Thang, member of the Party Central Committee, deputy secretary of the Hanoi Party Committee and chairman of the Hanoi People’s Committee, led a city delegation on May 18 to inspect preparations for Ba Vi National Park’s handover to the city and its subsequent management.
14:28 18/05/2026
Other news
Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region
Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region
On May 21, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha inspected the construction site and worked with departments, agencies and related units on the implementation progress of the second campus project of Hanoi Heart Hospital in Xuan Dinh Ward.
15:18 21/05/2026
Hanoi strengthens strategic partnership with Saint Petersburg through expanding legislative cooperation initiatives
Hanoi strengthens strategic partnership with Saint Petersburg through expanding legislative cooperation initiatives
As part of Hanoi’s 2026 foreign affairs agenda, a Hanoi delegation visited and worked in Saint Petersburg, Russia, from May 18 to May 20 at the invitation of the Legislative Assembly and the External Relations Committee of Saint Petersburg.
15:17 21/05/2026
Hanoi launches smart eco-industrial park advancing northern innovation and manufacturing growth ambitions
Hanoi launches smart eco-industrial park advancing northern innovation and manufacturing growth ambitions
On May 20, the Hanoi People's Committee and the Vietnam Construction and Import-Export Joint Stock Corporation (VINACONEX) broke ground on the Dong Anh Industrial Park infrastructure construction and business investment project.
15:18 20/05/2026
Hanoi steps up digital transformation and innovation in culture
Hanoi steps up digital transformation and innovation in culture
The Hanoi People's Committee Office has issued Notice No. 404/TB-VP, dated May 19, 2026, outlining conclusions by Vice Chairman of the Hanoi People's Committee Truong Viet Dung at a meeting reviewing digital transformation, science and technology, and innovation in the cultural sector.
15:16 19/05/2026
Hanoi launches major waste-to-energy plant advancing sustainable urban environmental transformation goals
Hanoi launches major waste-to-energy plant advancing sustainable urban environmental transformation goals
The Nui Thoong High-Tech Environmental Treatment and Waste-to-Energy Plant project is the first high-tech waste-to-energy plant project in southwestern Hanoi and is expected to become a strategic component in the capital's waste-to-energy development network.
15:10 19/05/2026
Hanoi honors veteran Party members for revolutionary dedication
Hanoi honors veteran Party members for revolutionary dedication
On the occasion of the 136th anniversary of President Ho Chi Minh's birth (May 19, 1890 - May 19, 2026), the Hanoi Party Committee on May 19 organized a ceremony to award 80-year, 75-year and 70-year Party membership badges in the May 19, 2026 recognition round.
15:10 19/05/2026
New highway corridor reshapes southern Hanoi with ambitious urban redevelopment vision
New highway corridor reshapes southern Hanoi with ambitious urban redevelopment vision
The project carries special significance for the city's strategy to develop urban space, strengthen regional connectivity and modernize southern Hanoi's infrastructure system in the new development phase.
15:09 19/05/2026
Hanoi strengthens strategic infrastructure cooperation with major Chinese construction corporation leaders
Hanoi strengthens strategic infrastructure cooperation with major Chinese construction corporation leaders
On May 18, Politburo member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang hosted a working session with Pacific Construction Group of China.
15:10 18/05/2026