Hanoi works to remove bottlenecks in site clearance for Ring Road 2.5 and Ring Road 3.5 projects

6:15 PM, Wed May 06, 2026

Central Party Committee Member, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee Vu Dai Thang on the morning of May 6 chaired a meeting to address difficulties and obstacles in site clearance for key projects on Ring Road 2.5 and Ring Road 3.5.

The meeting was attended by leaders from the city's departments and agencies. It was held in person at the headquarters of the Hanoi People's Committee and connected online to local authorities in wards and communes affected by the projects.

Hanoi works to remove bottlenecks in site clearance for Ring Road 2.5 and Ring Road 3.5 projects- Ảnh 1.Chairman of the Hanoi People's Committee Vu Dai Thang chairs the meeting

Many localities aim to complete site clearance before May 15

A report by Vu Xuan Tung, Deputy Director of the Hanoi Department of Agriculture and Environment, showed that site clearance for the Ring Road 2.5 and Ring Road 3.5 projects is being conducted intensively by local authorities. Most policy and regulatory obstacles have been addressed, helping accelerate progress on several key sections.

According to the report, Ring Road 2.5 includes 13 sections, of which six have completed site clearance, while the remaining seven are underway. On March 19, the Department of Agriculture and Environment issued Decision No. 651/QD-SNNMT to establish a task force to support site clearance for the remaining sections across seven wards.

Hanoi works to remove bottlenecks in site clearance for Ring Road 2.5 and Ring Road 3.5 projects- Ảnh 2.Deputy Director of the Hanoi Department of Agriculture and Environment Vu Xuan Tung reports at the meeting

Since March 20, the task force has worked directly with local authorities to assign responsibilities and resolve obstacles. Surveys and inspections have been completed, and several localities have largely completed compensation, support, and resettlement plans. Among the seven areas affected by Ring Road 2.5, Yen Hoa ward still has the largest workload.

Key sections, such as Linh Nam – Vinh Hoang, Dam Hong – Nguyen Trai, Cau Giay – Dich Vong, and Xuan Tao – Nam Thang Long, have largely completed compensation and resettlement arrangements.

Specifically, the Linh Nam – Vinh Hoang section has completed clearance in Vinh Hung ward, while payments are ongoing for 91 households in Hoang Mai ward, with completion expected before May 30, 2026. The Dam Hong – Nguyen Trai section has secured sufficient housing and land for resettlement, though some issues remain related to pricing approval and payment mechanisms.

Sections including Cau Giay – Dich Vong, Dich Vong – Duong Dinh Nghe, Vu Pham Ham – Tran Duy Hung, and Nguy Nhu Kon Tum – Nguyen Trai have built clearance plans with no remaining policy obstacles. Many localities have committed to completing work between May 15 and May 30, 2026.

Hanoi works to remove bottlenecks in site clearance for Ring Road 2.5 and Ring Road 3.5 projects- Ảnh 3.Ngo Ngoc Van, Director of the Hanoi Traffic Construction Investment Project Management Board, reports at the meeting

For Ring Road 3.5, the route runs from Quang Minh – Thien Loc – Thuong Cat Bridge – National Highway 32 – Thang Long Boulevard – National Highway 6 – National Highway 1A – Ngoc Hoi Bridge – Hung Yen. Two sections have been completed and put into operation, two are under preparation, while several bridges, interchanges, and other sections are currently undergoing site clearance.

The completed sections include the stretch from Thang Long Boulevard to Phuc La – Van Phu and from National Highway 32 to Thang Long Boulevard. Son Dong commune reported completing clearance for two industrial clusters, Doan Ket and Thanh Dung packaging, on April 24, 2026.

At Thuong Cat Bridge, clearance in Thien Loc commune is nearly complete, while the remaining work in Thuong Cat ward is expected to finish before May 15, 2026. Ngoc Hoi Bridge has completed 100% of site clearance on the Hanoi side, while work continues in Hung Yen.

Sections from Thuong Cat Bridge to National Highway 32 and from Phuc La – Van Phu to the Phap Van – Cau Gie Expressway are being built. The section passing through former Ha Dong has been approved but lacks funding, while the Thanh Tri section is completing investment procedures and environmental impact assessments. The interchange with Thang Long Boulevard has reached 99.8% completion and is expected to be operational before May 15, 2026.

According to the Department of Agriculture and Environment, most issues related to compensation, support, and resettlement for Ring Road 3.5 have been resolved. The city is also considering assigning a capable investor to implement the entire route in a coordinated manner, ensuring progress and connectivity.

Hanoi works to remove bottlenecks in site clearance for Ring Road 2.5 and Ring Road 3.5 projects- Ảnh 4.Dao Duy Phong, Deputy Director of the Hanoi Department of Construction, reports at the meeting

At the meeting, representatives from wards and communes, including Xuan Dinh, Kien Hung, Tay Tuu, Khuong Dinh, and Thien Loc, raised specific difficulties and proposed solutions related to site clearance and resettlement plans. Leaders from the Departments of Finance, Construction, and Agriculture and Environment directly addressed these concerns.

Accelerating progress to meet committed deadlines

In his concluding remarks, Chairman Vu Dai Thang acknowledged the strong consensus among local authorities, stressing the need for maximum effort during the final phase to ensure deadlines are met.

He noted that since the 18th Hanoi Party Congress, site clearance has received strong and consistent direction across the political system. Localities have mobilized resources and actively engaged residents to build consensus and hand over land for key projects.

Hanoi works to remove bottlenecks in site clearance for Ring Road 2.5 and Ring Road 3.5 projects- Ảnh 5.Chairman of the Hanoi People's Committee Vu Dai Thang delivers concluding remarks

Ring Road 2.5 and Ring Road 3.5 are critical transport corridors that must be completed soon to enhance regional connectivity and ease traffic congestion. The city praised the progress achieved so far, noting that most outstanding issues have been resolved or addressed with clear solutions.

In the coming period, Thang instructed local authorities to deploy resources and accelerate site clearance in line with committed timelines, aiming to complete many sections before May 15 and May 30, 2026. Priority will be given to public engagement and persuasion, ensuring social consensus.

Regarding policies and mechanisms, he directed departments to urgently resolve pending issues, particularly the approval of resettlement housing prices and the allocation of housing and land. "Progress must be accelerated so residents can quickly choose and settle into new homes," he stressed.

He also called for the planning and construction of resettlement areas to follow a modern approach, ensuring the living conditions are equal to or better than previous residences and avoiding infrastructure gaps between new urban areas and resettlement zones.

Project investors and management boards were instructed to begin construction immediately in areas where site clearance has been completed, preventing delays that could undermine public confidence.

For cases involving the relocation of businesses, factories, and industrial clusters, the city will study and issue appropriate support mechanisms to maintain production, employment, and livelihoods.

For large-scale developments such as the Olympic Sports Urban Area, the Chairman requested the development of specific policies for housing, resettlement, and social housing, ensuring systematic infrastructure and urban landscape.

In terms of implementation, the city will review and select capable investors while delegating authority to localities, with clear accountability attached. Independent site clearance projects are encouraged to create clean land for early construction.

As for social welfare, Thang instructed local authorities to pay special attention to vulnerable groups and disadvantaged households, ensuring timely support and preventing complex disputes during land recovery.

He praised the responsibility shown by local authorities and called for continued efforts to complete site clearance, contributing to infrastructure development and the socio-economic growth of the capital.

Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide

18:43 13/05/2026

The project will be implemented in coordination with other major infrastructure developments such as the expansion of National Highway 1A, urban railway systems and high-speed railways, creating strong momentum for modern urban development in southern Hanoi.

Most views
Same category
Find by date
Hanoi signs seven cooperation memorandums with Vientiane
Hanoi signs seven cooperation memorandums with Vientiane
Politburo member, Secretary of the Hanoi Party Committee, and Head of Hanoi's National Assembly delegation Tran Duc Thang, together with Central Committee member, Secretary of the Vientiane Party Committee, and Chairman of the Vientiane People's Council Athsaphangthong Siphandone, on May 12 co-chaired talks between high-level delegations from Hanoi and Vientiane, Laos at the Hanoi Party Committee headquarters.
18:38 12/05/2026
Hanoi expands healthcare support for children and people with disabilities at social protection centers
Hanoi expands healthcare support for children and people with disabilities at social protection centers
The Hanoi Department of Health on May 12 organized a healthcare examination and support program for children and people with disabilities currently being cared for at social protection centers across the city at the Hanoi Center for the Care of People With Disabilities.
18:37 12/05/2026
Hanoi and Vientiane share experience on elected council operations
Hanoi and Vientiane share experience on elected council operations
Phung Thi Hong Ha, Deputy Secretary of the Hanoi Party Committee, Chairwoman of the Hanoi People's Council, and Deputy Head of Hanoi's National Assembly delegation, on May 12 hosted and held talks with a high-level delegation from Vientiane, Laos, led by Atsaphangthong Siphandone, member of the Lao People's Revolutionary Party Central Committee, Secretary of the Vientiane Party Committee, and Chairman of the Vientiane People's Council.
18:37 12/05/2026
Son Dong and Chuyen My craft villages join World Crafts Cities Creative Network
Son Dong and Chuyen My craft villages join World Crafts Cities Creative Network
The Hanoi People's Committee, on the evening of May 8, held a ceremony to celebrate the inclusion of Chuyen My mother-of-pearl inlay and lacquerware village and Son Dong lacquer sculpture village as members of the World Crafts Cities Creative Network at the Thang Long Imperial Citadel.
18:32 08/05/2026
Hanoi and Danang exchange experience in developing capital's 100-year master plan
Hanoi and Danang exchange experience in developing capital's 100-year master plan
Duong Duc Tuan, member of the Standing Board of the Hanoi Party Committee and Permanent Vice Chairman of the Hanoi People's Committee, and Le Quang Nam, Vice Chairman of the Danang People's Committee, on the morning of May 8 co-chaired a conference to exchange work experience and discuss the development of Hanoi's 100-year Capital Master Plan at the Hanoi People's Committee headquarters.
18:31 08/05/2026
Hanoi finalizes 20 key documents to implement 2026 Capital Law in science, technology, innovation, and digital transformation
Hanoi finalizes 20 key documents to implement 2026 Capital Law in science, technology, innovation, and digital transformation
Politburo member, Secretary of the Hanoi Party Committee, and Head of the Hanoi National Assembly Delegation Tran Duc Thang, who also serves as Head of the Steering Committee for implementing Resolution No. 57-NQ/TW dated December 22, 2024, issued by the Politburo on breakthroughs in science, technology, innovation, and national digital transformation in Hanoi (Steering Committee 57), chaired the committee's May monthly review meeting on the morning of May 8.
18:30 08/05/2026
Other news
Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide
Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide
The project will be implemented in coordination with other major infrastructure developments such as the expansion of National Highway 1A, urban railway systems and high-speed railways, creating strong momentum for modern urban development in southern Hanoi.
18:43 13/05/2026
Vientiane leader honors President Ho Chi Minh, strengthens bilateral friendship with Hanoi
Vientiane leader honors President Ho Chi Minh, strengthens bilateral friendship with Hanoi
On May 12, a high-level delegation from Vientiane Capital, led by Athsaphangthong Siphandone, member of the Party Central Committee, Secretary of the Vientiane Party Committee and Chairman of the Vientiane People's Council, paid tribute at the Mausoleum of President Ho Chi Minh.
18:46 12/05/2026
Dong Da Ward launches community legal support model to bring public services closer to residents
Dong Da Ward launches community legal support model to bring public services closer to residents
The model is expected to help residents complete administrative procedures conveniently and in compliance with regulations, while also providing legal consultation and guidance in areas such as civil matters, civil status, land issues, marriage and family and social welfare.
18:44 12/05/2026
Hanoi launches healthcare program supporting ethnic minority children in remote mountainous communities
Hanoi launches healthcare program supporting ethnic minority children in remote mountainous communities
On May 12, at Ba Trai A Kindergarten, the Hanoi Department of Health coordinated with the Suoi Hai Commune People's Committee to organize a healthcare and medical examination program for children in ethnic minority and mountainous communes as part of the 2026 Action Month for Children.
18:42 12/05/2026
Hanoi launches program to maintain replacement fertility rate through 2030
Hanoi launches program to maintain replacement fertility rate through 2030
Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha has signed Plan No. 189/KH-UBND, dated May 12, 2026, on implementing the "Program to Maintain Replacement Fertility Rate in Hanoi Through 2030."
18:39 12/05/2026
Hanoi approves resolution guiding legal implementation mechanisms under 2026 Capital Law framework
Hanoi approves resolution guiding legal implementation mechanisms under 2026 Capital Law framework
On May 11, during its second session, the 17th Hanoi People's Council unanimously passed a resolution regulating several issues related to drafting and issuing legal normative documents to implement the Capital Law.
18:46 11/05/2026
Hanoi establishes Steering Committee on Waste Prevention and Control
Hanoi establishes Steering Committee on Waste Prevention and Control
Chairman of the Hanoi People's Committee Vu Dai Thang has signed Decision No. 2415/QD-UBND, dated May 11, 2026, establishing the Hanoi Steering Committee on Waste Prevention and Control.
18:41 11/05/2026
Hanoi community music program brings culture closer to everyday urban life naturally
Hanoi community music program brings culture closer to everyday urban life naturally
On May 10, at the Octagonal House, the "Community Music" program delivered an emotional evening of music featuring melodies about the homeland, the country and maternal love.
18:33 10/05/2026