These projects are considered critical to completing the Capital's transport infrastructure, easing pressure on crossings over the Red River, while opening up new urban development space and driving growth on both riverbanks.

Chairman of the Hanoi People's Committee Vu Dai Thang (fourth from left) inspects the progress of the Tu Lien Bridge and access road project. Photo: Le Hai
Strong local consensus accelerates land clearance
Reporting at the site, Bui Tuan Anh, Secretary of the Hong Ha Ward Party Committee and Chairman of the Ward People’s Council, said land clearance for the two projects has reached around 95%, largely meeting the planned schedule.
He noted that despite the large workload and tight timeline, strong direction from the city and coordinated efforts across agencies, along with active engagement from grassroots political organizations, have delivered positive results. Local officials and mass organizations have worked directly with residents, addressing cases individually.
“We sincerely thank residents who have long lived here but still support the policy, accept compensation and hand over land for the projects,” Bui Tuan Anh said.
Authorities have held direct dialogues with affected households to address concerns within the policy framework, while escalating issues beyond their authority to the city for timely resolution.
The ward aims to complete key items before April 15 and resolve all remaining issues by April 30, while continuing to finalize resettlement procedures to ensure social stability.

Chairman Vu Dai Thang calls for ensuring the maximum legitimate rights of residents during land acquisition and resettlement. Photo: Le Hai
On-site observations show strong public support, with many households proactively relocating early, a key factor in accelerating land clearance.
Large-scale projects push construction forward
According to the Hanoi Traffic Construction Investment Project Management Board, the Tu Lien Bridge and access road project spans about 5.15 kilometers, with total investment exceeding VND15,498 billion (US$619 million).
Land clearance has reached nearly 80% of the total area, including over 63% in Hong Ha Ward. Construction is underway at 14 sites along the route, covering the main cable-stayed bridge, cantilever sections, approach bridges, tunnels, and technical infrastructure.
Key components such as bored piles for main piers, underpasses, and the Nghi Tam interchange are being implemented simultaneously. The project targets completion and operation in the second quarter of 2027, provided land is handed over on schedule.

Land clearance for the Tu Lien Bridge and access road project has reached nearly 80% of the total area. Photo: Le Hai
For the Tran Hung Dao Bridge project, the total length is about 4.18 kilometers, featuring a modern steel arch design with six lanes for motor vehicles, along with lanes for bicycles and pedestrians.
The project has a total investment of approximately VND16,226 billion (US$648 million) and is being implemented under a public-private partnership model. Land clearance is ongoing across multiple wards, with about 30.95 hectares to be acquired.
Construction activities, including bored piles, pier foundations, approach bridges, and auxiliary works, are underway. The overall schedule also targets completion in the second quarter of 2027, in time for major national events.

Photo 4: Chairman Vu Dai Thang inspects the Tran Hung Dao Bridge project. Photo: Le Hai
However, both projects still face challenges, mainly due to uneven land handover, relocation of underground and overhead utilities, and issues related to defense land and power infrastructure.
Investors ready to build once land is handed over
Nguyen Nam Thuy, head of the Tran Hung Dao Bridge project management board, said the investor is fully prepared to begin construction as soon as land becomes available.
He noted that the most critical bottleneck is the TC1 pier area, where local authorities are working to secure land handover. Once this section is cleared, the entire main bridge construction can proceed simultaneously.

The investor is ready to begin construction immediately once land is handed over. Photo: Pham Linh
Machinery, equipment, and workforce are already in place, with construction set to start immediately upon receiving land, ensuring flood-season timelines are met and the bridge is completed by the second quarter of 2027.
Contractors are also adjusting technical plans to match the actual pace of land clearance, avoiding disruptions to the overall schedule.
Removing bottlenecks to accelerate progress
During the inspection, Chairman Vu Dai Thang praised the efforts of local authorities, project owners, and contractors in advancing these key projects.
He stressed that the Tu Lien and Tran Hung Dao bridges are not only transport projects but also strategic works aimed at removing infrastructure bottlenecks, expanding urban space and improving living standards.
The Chairman called for closer coordination among relevant agencies, with a focus on resolving outstanding issues, particularly land clearance, which he described as the decisive factor for project timelines.
Local authorities were urged to accelerate land clearance and ensure that handed-over land is fully cleared, while continuing public outreach to maintain consensus.
At the same time, the city must ensure the maximum legitimate rights of affected residents and promptly address complaints to prevent social tensions.

Chairman Vu Dai Thang listens to residents' concerns in land clearance areas for the Tran Hung Dao Bridge project. Photo: Pham Linh
Project investors and contractors were instructed to review schedules, develop detailed construction plans, and mobilize maximum resources, starting work immediately wherever land is available.
Environmental protection during construction was also emphasized, with strict control required over material transport, dust, noise, and waste, following the principle of "clean construction at every stage."
Targeting completion in Q2 2027
Concluding the inspection, Chairman Vu Dai Thang called on all levels of government, investors, and contractors to make maximum efforts to meet project deadlines.
Land clearance must be completed as committed, while issues related to utilities, defense land, and power systems must be resolved promptly.
The overarching goal is to complete and put both bridges into operation in the second quarter of 2027, contributing to a more complete transport network, stronger economic growth, and improved quality of life for Hanoi residents.

Land clearance for the Tu Lien Bridge project is being accelerated by local authorities and relevant units. Photo: Pham Linh
The inspection underscored a strong, coordinated approach and broad public support. With alignment between authorities, businesses, and residents, these major projects are expected not only to meet deadlines but also to become symbols of Hanoi's modern and sustainable development in the coming years.