Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects

10:01 AM, Tue April 14, 2026

Chairman of the Hanoi People's Committee Vu Dai Thang on April 14 conducted an on-site inspection of land clearance, resettlement arrangements, and construction progress for two major transport projects, Tu Lien Bridge and Tran Hung Dao Bridge, in Hong Ha Ward.

These projects are considered critical to completing the Capital's transport infrastructure, easing pressure on crossings over the Red River, while opening up new urban development space and driving growth on both riverbanks.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 1.

Chairman of the Hanoi People's Committee Vu Dai Thang (fourth from left) inspects the progress of the Tu Lien Bridge and access road project. Photo: Le Hai

Strong local consensus accelerates land clearance

Reporting at the site, Bui Tuan Anh, Secretary of the Hong Ha Ward Party Committee and Chairman of the Ward People’s Council, said land clearance for the two projects has reached around 95%, largely meeting the planned schedule.

He noted that despite the large workload and tight timeline, strong direction from the city and coordinated efforts across agencies, along with active engagement from grassroots political organizations, have delivered positive results. Local officials and mass organizations have worked directly with residents, addressing cases individually.

“We sincerely thank residents who have long lived here but still support the policy, accept compensation and hand over land for the projects,” Bui Tuan Anh said.

Authorities have held direct dialogues with affected households to address concerns within the policy framework, while escalating issues beyond their authority to the city for timely resolution.

The ward aims to complete key items before April 15 and resolve all remaining issues by April 30, while continuing to finalize resettlement procedures to ensure social stability.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 2.

Chairman Vu Dai Thang calls for ensuring the maximum legitimate rights of residents during land acquisition and resettlement. Photo: Le Hai

On-site observations show strong public support, with many households proactively relocating early, a key factor in accelerating land clearance.

Large-scale projects push construction forward

According to the Hanoi Traffic Construction Investment Project Management Board, the Tu Lien Bridge and access road project spans about 5.15 kilometers, with total investment exceeding VND15,498 billion (US$619 million).

Land clearance has reached nearly 80% of the total area, including over 63% in Hong Ha Ward. Construction is underway at 14 sites along the route, covering the main cable-stayed bridge, cantilever sections, approach bridges, tunnels, and technical infrastructure.

Key components such as bored piles for main piers, underpasses, and the Nghi Tam interchange are being implemented simultaneously. The project targets completion and operation in the second quarter of 2027, provided land is handed over on schedule.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 3.

Land clearance for the Tu Lien Bridge and access road project has reached nearly 80% of the total area. Photo: Le Hai

For the Tran Hung Dao Bridge project, the total length is about 4.18 kilometers, featuring a modern steel arch design with six lanes for motor vehicles, along with lanes for bicycles and pedestrians.

The project has a total investment of approximately VND16,226 billion (US$648 million) and is being implemented under a public-private partnership model. Land clearance is ongoing across multiple wards, with about 30.95 hectares to be acquired.

Construction activities, including bored piles, pier foundations, approach bridges, and auxiliary works, are underway. The overall schedule also targets completion in the second quarter of 2027, in time for major national events.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 4.

Photo 4: Chairman Vu Dai Thang inspects the Tran Hung Dao Bridge project. Photo: Le Hai

However, both projects still face challenges, mainly due to uneven land handover, relocation of underground and overhead utilities, and issues related to defense land and power infrastructure.

Investors ready to build once land is handed over

Nguyen Nam Thuy, head of the Tran Hung Dao Bridge project management board, said the investor is fully prepared to begin construction as soon as land becomes available.

He noted that the most critical bottleneck is the TC1 pier area, where local authorities are working to secure land handover. Once this section is cleared, the entire main bridge construction can proceed simultaneously.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 5.

The investor is ready to begin construction immediately once land is handed over. Photo: Pham Linh

Machinery, equipment, and workforce are already in place, with construction set to start immediately upon receiving land, ensuring flood-season timelines are met and the bridge is completed by the second quarter of 2027.

Contractors are also adjusting technical plans to match the actual pace of land clearance, avoiding disruptions to the overall schedule.

Removing bottlenecks to accelerate progress

During the inspection, Chairman Vu Dai Thang praised the efforts of local authorities, project owners, and contractors in advancing these key projects.

He stressed that the Tu Lien and Tran Hung Dao bridges are not only transport projects but also strategic works aimed at removing infrastructure bottlenecks, expanding urban space and improving living standards.

The Chairman called for closer coordination among relevant agencies, with a focus on resolving outstanding issues, particularly land clearance, which he described as the decisive factor for project timelines.

Local authorities were urged to accelerate land clearance and ensure that handed-over land is fully cleared, while continuing public outreach to maintain consensus.

At the same time, the city must ensure the maximum legitimate rights of affected residents and promptly address complaints to prevent social tensions.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 6.

Chairman Vu Dai Thang listens to residents' concerns in land clearance areas for the Tran Hung Dao Bridge project. Photo: Pham Linh

Project investors and contractors were instructed to review schedules, develop detailed construction plans, and mobilize maximum resources, starting work immediately wherever land is available.

Environmental protection during construction was also emphasized, with strict control required over material transport, dust, noise, and waste, following the principle of "clean construction at every stage."

Targeting completion in Q2 2027

Concluding the inspection, Chairman Vu Dai Thang called on all levels of government, investors, and contractors to make maximum efforts to meet project deadlines.

Land clearance must be completed as committed, while issues related to utilities, defense land, and power systems must be resolved promptly.

The overarching goal is to complete and put both bridges into operation in the second quarter of 2027, contributing to a more complete transport network, stronger economic growth, and improved quality of life for Hanoi residents.

Hanoi Chairman Vu Dai Thang inspects progress of Tu Lien and Tran Hung Dao bridge projects- Ảnh 7.

Land clearance for the Tu Lien Bridge project is being accelerated by local authorities and relevant units. Photo: Pham Linh

The inspection underscored a strong, coordinated approach and broad public support. With alignment between authorities, businesses, and residents, these major projects are expected not only to meet deadlines but also to become symbols of Hanoi's modern and sustainable development in the coming years.

Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide

18:43 13/05/2026

The project will be implemented in coordination with other major infrastructure developments such as the expansion of National Highway 1A, urban railway systems and high-speed railways, creating strong momentum for modern urban development in southern Hanoi.

Most views
Same category
Find by date
Hanoi signs seven cooperation memorandums with Vientiane
Hanoi signs seven cooperation memorandums with Vientiane
Politburo member, Secretary of the Hanoi Party Committee, and Head of Hanoi's National Assembly delegation Tran Duc Thang, together with Central Committee member, Secretary of the Vientiane Party Committee, and Chairman of the Vientiane People's Council Athsaphangthong Siphandone, on May 12 co-chaired talks between high-level delegations from Hanoi and Vientiane, Laos at the Hanoi Party Committee headquarters.
18:38 12/05/2026
Hanoi expands healthcare support for children and people with disabilities at social protection centers
Hanoi expands healthcare support for children and people with disabilities at social protection centers
The Hanoi Department of Health on May 12 organized a healthcare examination and support program for children and people with disabilities currently being cared for at social protection centers across the city at the Hanoi Center for the Care of People With Disabilities.
18:37 12/05/2026
Hanoi and Vientiane share experience on elected council operations
Hanoi and Vientiane share experience on elected council operations
Phung Thi Hong Ha, Deputy Secretary of the Hanoi Party Committee, Chairwoman of the Hanoi People's Council, and Deputy Head of Hanoi's National Assembly delegation, on May 12 hosted and held talks with a high-level delegation from Vientiane, Laos, led by Atsaphangthong Siphandone, member of the Lao People's Revolutionary Party Central Committee, Secretary of the Vientiane Party Committee, and Chairman of the Vientiane People's Council.
18:37 12/05/2026
Son Dong and Chuyen My craft villages join World Crafts Cities Creative Network
Son Dong and Chuyen My craft villages join World Crafts Cities Creative Network
The Hanoi People's Committee, on the evening of May 8, held a ceremony to celebrate the inclusion of Chuyen My mother-of-pearl inlay and lacquerware village and Son Dong lacquer sculpture village as members of the World Crafts Cities Creative Network at the Thang Long Imperial Citadel.
18:32 08/05/2026
Hanoi and Danang exchange experience in developing capital's 100-year master plan
Hanoi and Danang exchange experience in developing capital's 100-year master plan
Duong Duc Tuan, member of the Standing Board of the Hanoi Party Committee and Permanent Vice Chairman of the Hanoi People's Committee, and Le Quang Nam, Vice Chairman of the Danang People's Committee, on the morning of May 8 co-chaired a conference to exchange work experience and discuss the development of Hanoi's 100-year Capital Master Plan at the Hanoi People's Committee headquarters.
18:31 08/05/2026
Hanoi finalizes 20 key documents to implement 2026 Capital Law in science, technology, innovation, and digital transformation
Hanoi finalizes 20 key documents to implement 2026 Capital Law in science, technology, innovation, and digital transformation
Politburo member, Secretary of the Hanoi Party Committee, and Head of the Hanoi National Assembly Delegation Tran Duc Thang, who also serves as Head of the Steering Committee for implementing Resolution No. 57-NQ/TW dated December 22, 2024, issued by the Politburo on breakthroughs in science, technology, innovation, and national digital transformation in Hanoi (Steering Committee 57), chaired the committee's May monthly review meeting on the morning of May 8.
18:30 08/05/2026
Other news
Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide
Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide
The project will be implemented in coordination with other major infrastructure developments such as the expansion of National Highway 1A, urban railway systems and high-speed railways, creating strong momentum for modern urban development in southern Hanoi.
18:43 13/05/2026
Vientiane leader honors President Ho Chi Minh, strengthens bilateral friendship with Hanoi
Vientiane leader honors President Ho Chi Minh, strengthens bilateral friendship with Hanoi
On May 12, a high-level delegation from Vientiane Capital, led by Athsaphangthong Siphandone, member of the Party Central Committee, Secretary of the Vientiane Party Committee and Chairman of the Vientiane People's Council, paid tribute at the Mausoleum of President Ho Chi Minh.
18:46 12/05/2026
Dong Da Ward launches community legal support model to bring public services closer to residents
Dong Da Ward launches community legal support model to bring public services closer to residents
The model is expected to help residents complete administrative procedures conveniently and in compliance with regulations, while also providing legal consultation and guidance in areas such as civil matters, civil status, land issues, marriage and family and social welfare.
18:44 12/05/2026
Hanoi launches healthcare program supporting ethnic minority children in remote mountainous communities
Hanoi launches healthcare program supporting ethnic minority children in remote mountainous communities
On May 12, at Ba Trai A Kindergarten, the Hanoi Department of Health coordinated with the Suoi Hai Commune People's Committee to organize a healthcare and medical examination program for children in ethnic minority and mountainous communes as part of the 2026 Action Month for Children.
18:42 12/05/2026
Hanoi launches program to maintain replacement fertility rate through 2030
Hanoi launches program to maintain replacement fertility rate through 2030
Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha has signed Plan No. 189/KH-UBND, dated May 12, 2026, on implementing the "Program to Maintain Replacement Fertility Rate in Hanoi Through 2030."
18:39 12/05/2026
Hanoi approves resolution guiding legal implementation mechanisms under 2026 Capital Law framework
Hanoi approves resolution guiding legal implementation mechanisms under 2026 Capital Law framework
On May 11, during its second session, the 17th Hanoi People's Council unanimously passed a resolution regulating several issues related to drafting and issuing legal normative documents to implement the Capital Law.
18:46 11/05/2026
Hanoi establishes Steering Committee on Waste Prevention and Control
Hanoi establishes Steering Committee on Waste Prevention and Control
Chairman of the Hanoi People's Committee Vu Dai Thang has signed Decision No. 2415/QD-UBND, dated May 11, 2026, establishing the Hanoi Steering Committee on Waste Prevention and Control.
18:41 11/05/2026
Hanoi community music program brings culture closer to everyday urban life naturally
Hanoi community music program brings culture closer to everyday urban life naturally
On May 10, at the Octagonal House, the "Community Music" program delivered an emotional evening of music featuring melodies about the homeland, the country and maternal love.
18:33 10/05/2026