Hanoi Party Chief urges acceleration of key projects to improve livelihoods and remove urban bottlenecks

6:10 PM, Sun May 03, 2026

On May 3, Tran Duc Thang, Politburo member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly delegation, inspected the progress of several projects across the city.

Hanoi Party Chief urges acceleration of key projects to improve livelihoods and remove urban bottlenecks- Ảnh 1.

Hanoi Party Chief Tran Duc Thang inspects the progress of the Phu Do regulating lake project in Tu Liem Ward.

The projects included the Phu Do regulating lake project; the Me Tri headwater lake project (Dong Bong 2 Lake); the construction of the Thang Long Boulevard expressway section connecting National Highway 21 to the Hanoi–Hoa Binh Expressway; the Vietnam National University campus in Hoa Lac; and the Seraphin waste-to-energy plant project at the Xuan Son solid waste treatment complex.

Joining the delegation were Central Party Committee member and Standing Vice Secretary of the Hanoi Party Committee Nguyen Trong Dong; Major General Dao Van Nhan, member of the Hanoi Party Committee Standing Board and Commander of the Hanoi Capital Command; and Vice Chairman of the Hanoi People's Committee Truong Viet Dung.

The Phu Do regulating lake project in Tu Liem Ward has a water surface area of 31.5 hectares and a total construction land area of about 36.76 hectares, with an embankment surrounding the lake stretching approximately 2,684 meters.

The project includes two box culverts for regulating water inflow and outflow, a box culvert connecting the lake to the Nhue River equipped with two temporary pumps, and a regulating gate prepared for connection to Nguyen Van Giap Road leading to the Dong Bong pumping station.

A 3-meter-wide walking path circles the lake, featuring railings, lighting systems, trees and surrounding grass areas.

The project has a total investment of VND1.167 trillion ($44.3 million) from the city budget. Construction began in the first quarter of 2026 and is scheduled for completion in the fourth quarter of 2026, with key components to be finished before the 2026 rainy season.

To date, approximately 35.28 out of 36.76 hectares, or 96% of the site, are ready for construction. Contractors are waiting for the relocation of power lines and the connection of five substations within the lake area.

Regarding key components, contractors have excavated some 1.284 million out of 1.44 million cubic meters of the lake bed, reaching 89% and transported 1.284 million out of 1.46 million cubic meters of soil, also reaching 89%.

Construction of embankments and drainage systems is underway. Stone masonry at the outlet has been completed and the culvert base has been concreted. Reinforcement for culvert walls connecting to the drainage system leading to the Nhue River is in progress. Two pumps have been manufactured.

For key drainage components, excavation and soil transport are expected to be completed before May 15, 2026, along with the installation of SW400B sheet piles.

For the remaining components, contractors are deploying multiple construction teams simultaneously, aiming to complete all work before June 30, 2026.

Hanoi Party Chief urges acceleration of key projects to improve livelihoods and remove urban bottlenecks- Ảnh 2.

Hanoi Party Chief Tran Duc Thang visits the Me Tri headwater lake project in Dai Mo Ward.

The Me Tri headwater lake project, Dong Bong 2 Lake, in Dai Mo Ward has a water surface area of about 12 hectares, with a water level elevation of 5.1 meters and an embankment approximately 1,950 meters long, along with culverts and regulating gates.

The project has a total investment of over VND601 billion ($22.8 million) from the city budget. Construction began in the first quarter of 2026 and is scheduled for completion in the fourth quarter of 2026, with major components to be completed before the 2026 rainy season.

To date, Dai Mo Ward has handed over 100% of the cleared site area, totaling 17.38 hectares. By April 30, 2026, key components such as the surrounding embankment, excavation and transport of soil and water intake and drainage systems connected to the Dong Bong canal have been largely completed.

The remaining components, including finishing the embankment crest, slopes, railings and walking paths around the lake, are scheduled for completion before June 30, 2026.

The Thang Long Boulevard expressway construction project connecting National Highway 21 to the Hanoi–Hoa Binh Expressway is a Group A project and a special-grade road transport project.

The project is approximately 6.7 kilometers long, with a cross-section width ranging from 120 to 161 meters, built in full alignment with the approved master plan.

The route includes four bridges and five tunnels, including one mainline underpass for the expressway and four cross underpasses for local traffic.

The total investment is VND5.25 trillion ($199.4 million), funded by the city budget and central government support, including VND2.7 trillion ($102.6 million) for site clearance.

So far, local authorities have handed over 93.09 out of 101.18 hectares, reaching 92%. However, some land users have not yet received approved compensation plans and have not agreed to relocate assets or demolish structures.

The project has three main construction packages. The goal is to open the parallel road section before June 30, 2026 and complete the entire project within 2026 as directed by the Hanoi Party Committee.

Challenges remain in site clearance at three locations: the K5 fuel depot covering 3.84 hectares, the C5 production facility covering 0.66 hectares and residential areas in Tan Binh Hamlet at Yen Binh intersection and Mieu intersection.

Hanoi Party Chief urges acceleration of key projects to improve livelihoods and remove urban bottlenecks- Ảnh 3.

Hanoi Party Chief Tran Duc Thang speaks to local authorities and contractors involved in the Thang Long Boulevard expressway construction project.

The Hanoi Department of Agriculture and Environment will coordinate with the two communes to guide policies on site clearance, resettlement and related challenges.

The Seraphin waste-to-energy plant, developed by Seraphin Green Environmental Technology Joint Stock Company, a member of AMACCAO Group, has a processing capacity of 2,250 tons per day and power generation capacity of 37 MW, with a total investment of VND4.85 trillion ($184.4 million).

The plant began receiving and processing household waste on May 1, 2025 and started supplying electricity to the national grid on July 1, 2025.

From May 1, 2025 to April 28, 2026, the plant processed 609,485.36 tons of household waste and generated 226,570.6 MWh of electricity. Ash output reached 96,944.21 tons, with 12,830.83 tons of solidified fly ash.

Seraphin is the first large-scale waste-to-energy project in Vietnam fully developed by a domestic enterprise.

The AMACCAO – Thanh Cong waste treatment and power generation plant is being developed by AMACCAO – Thanh Cong Renewable Energy Joint Stock Company.

The project has a capacity of 800 tons of waste per day, including 200 tons of industrial solid waste and 50 tons of hazardous waste per day. Its power generation capacity is 20 MW, with a total investment of VND3 trillion ($114 million).

On January 30, 2026, the Hanoi Department of Finance issued the investment registration certificate for the project at the Xuan Son solid waste treatment complex in Tung Thien Ward.

The investor is currently relocating and dismantling equipment and demolishing the old plant to clear the site for construction once conditions are met.

The goal is to begin waste processing operations by the National Day on September 2, 2027 and achieve full operation at least five months ahead of the originally approved timeline.

The Xuan Son solid waste treatment complex has been used for landfill operations for 20 years and is now severely polluted, affecting residents in the former Son Tay Town and Ba Vi Commune areas.

AMACCAO Group has proposed a project to rehabilitate and restore the environment at the Xuan Son site, aiming to incinerate legacy waste and transform the landfill area into green parks and themed parks.

The proposed project covers approximately 186 hectares, including the existing landfill and a 500-meter environmental impact buffer zone, with an estimated investment of VND2.300 trillion ($87.3 million) under a build-transfer contract model.

Speaking at the project sites, Hanoi Party Secretary Tran Duc Thang praised the efforts of departments, investors and contractors in overcoming challenges to accelerate project progress.

For the Phu Do regulating lake project, he emphasized that it is being implemented under urgent orders and is intended to address flooding during the 2026 rainy season.

Hanoi Party Chief urges acceleration of key projects to improve livelihoods and remove urban bottlenecks- Ảnh 4.

Hanoi Party Chief Tran Duc Thang visits the Seraphin waste-to-energy plant project at the Xuan Son solid waste treatment complex.

He stressed that all project activities must proceed with urgency to meet immediate flood prevention needs and directed Tu Liem Ward to complete the remaining site clearance by May 15, 2026.

Investors and contractors were instructed to mobilize resources to accelerate construction while ensuring quality and safety, with the goal of completing the project by the end of June 2026.

Thang also instructed relevant agencies to urgently develop mechanisms and policies for handling excavated soil suitable for reuse in regulating lake projects, facilitating faster progress.

At the Me Tri headwater lake project, he required contractors to meet their commitments by completing the lake basin before May 10, 2026 and finishing landscaping and walking paths before June 30, 2026.

At the Thang Long Boulevard expressway project, the Hanoi Party Chief highlighted its strategic importance for the development of western Hanoi.

To meet the schedule, he required contractors to complete the route by June 30, 2026.

Thang also instructed Hoa Lac and Yen Xuan communes to complete site clearance for the remaining areas before May 10, 2026.

Relevant departments were tasked with promptly allocating funds for resettlement areas for affected residents.

At the Seraphin waste-to-energy plant, he praised its large-scale operations and its role in addressing the city's waste challenges using modern technology.

Thang commended AMACCAO Group for its determination in successfully implementing the project, benefiting businesses, the city and residents while supporting long-term environmental sustainability.

Regarding the AMACCAO – Thanh Cong plant, he urged relevant agencies to guide the investor in promptly completing the required procedures.

The Hanoi Party Chief set a target for the city to have an additional waste-to-energy plant by mid-2027.

On environmental treatment at the Xuan Son site, he stated that the proposal to process landfill waste aligns with the city's goal of building a clean and green environment.

He assigned the Hanoi People's Committee and relevant agencies to guide the necessary procedures for implementation.

Thang also encouraged AMACCAO Group to continue improving workers' quality of life and maintaining environmental standards during plant operations.

On this occasion, Tran Duc Thang and the city delegation, together with leaders of Vietnam National University, inspected several areas within the university campus in Hoa Lac.

Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide

18:43 13/05/2026

The project will be implemented in coordination with other major infrastructure developments such as the expansion of National Highway 1A, urban railway systems and high-speed railways, creating strong momentum for modern urban development in southern Hanoi.

Most views
Same category
Find by date
Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide
Hanoi pushes Olympic sports urban project progress while accelerating land clearance efforts citywide
The project will be implemented in coordination with other major infrastructure developments such as the expansion of National Highway 1A, urban railway systems and high-speed railways, creating strong momentum for modern urban development in southern Hanoi.
18:43 13/05/2026
Hanoi launches healthcare program supporting ethnic minority children in remote mountainous communities
Hanoi launches healthcare program supporting ethnic minority children in remote mountainous communities
On May 12, at Ba Trai A Kindergarten, the Hanoi Department of Health coordinated with the Suoi Hai Commune People's Committee to organize a healthcare and medical examination program for children in ethnic minority and mountainous communes as part of the 2026 Action Month for Children.
18:42 12/05/2026
Hanoi community music program brings culture closer to everyday urban life naturally
Hanoi community music program brings culture closer to everyday urban life naturally
On May 10, at the Octagonal House, the "Community Music" program delivered an emotional evening of music featuring melodies about the homeland, the country and maternal love.
18:33 10/05/2026
World Crafts Council delegation visits Hanoi's historic Trach Xa traditional ao dai tailoring village
World Crafts Council delegation visits Hanoi's historic Trach Xa traditional ao dai tailoring village
Trach Xa Village in Ung Hoa Commune is one of Hanoi's most famous and long-standing traditional ao dai tailoring villages and is considered the cradle of traditional Vietnamese ao dai tailoring.
18:33 10/05/2026
Hanoi and Yamanashi boost cooperation in green growth, culture and education
Hanoi and Yamanashi boost cooperation in green growth, culture and education
On May 10, Party Central Committee member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang received a delegation from Yamanashi Prefecture, Japan, led by Governor Nagasaki Kotaro, to discuss areas of mutual cooperation.
18:27 10/05/2026
Hanoi leaders inspect metro operations, speed up underground station construction
Hanoi leaders inspect metro operations, speed up underground station construction
On May 9, Politburo member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang conducted an on-site inspection of management, operation, integrated ticketing and exploitation activities on the elevated section of Urban Railway Line 3.1 from Nhon to Cau Giay.
18:29 09/05/2026
Other news
Vientiane leader honors President Ho Chi Minh, strengthens bilateral friendship with Hanoi
Vientiane leader honors President Ho Chi Minh, strengthens bilateral friendship with Hanoi
On May 12, a high-level delegation from Vientiane Capital, led by Athsaphangthong Siphandone, member of the Party Central Committee, Secretary of the Vientiane Party Committee and Chairman of the Vientiane People's Council, paid tribute at the Mausoleum of President Ho Chi Minh.
18:46 12/05/2026
Dong Da Ward launches community legal support model to bring public services closer to residents
Dong Da Ward launches community legal support model to bring public services closer to residents
The model is expected to help residents complete administrative procedures conveniently and in compliance with regulations, while also providing legal consultation and guidance in areas such as civil matters, civil status, land issues, marriage and family and social welfare.
18:44 12/05/2026
Hanoi launches program to maintain replacement fertility rate through 2030
Hanoi launches program to maintain replacement fertility rate through 2030
Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha has signed Plan No. 189/KH-UBND, dated May 12, 2026, on implementing the "Program to Maintain Replacement Fertility Rate in Hanoi Through 2030."
18:39 12/05/2026
Hanoi signs seven cooperation memorandums with Vientiane
Hanoi signs seven cooperation memorandums with Vientiane
Politburo member, Secretary of the Hanoi Party Committee, and Head of Hanoi's National Assembly delegation Tran Duc Thang, together with Central Committee member, Secretary of the Vientiane Party Committee, and Chairman of the Vientiane People's Council Athsaphangthong Siphandone, on May 12 co-chaired talks between high-level delegations from Hanoi and Vientiane, Laos at the Hanoi Party Committee headquarters.
18:38 12/05/2026
Hanoi expands healthcare support for children and people with disabilities at social protection centers
Hanoi expands healthcare support for children and people with disabilities at social protection centers
The Hanoi Department of Health on May 12 organized a healthcare examination and support program for children and people with disabilities currently being cared for at social protection centers across the city at the Hanoi Center for the Care of People With Disabilities.
18:37 12/05/2026
Hanoi and Vientiane share experience on elected council operations
Hanoi and Vientiane share experience on elected council operations
Phung Thi Hong Ha, Deputy Secretary of the Hanoi Party Committee, Chairwoman of the Hanoi People's Council, and Deputy Head of Hanoi's National Assembly delegation, on May 12 hosted and held talks with a high-level delegation from Vientiane, Laos, led by Atsaphangthong Siphandone, member of the Lao People's Revolutionary Party Central Committee, Secretary of the Vientiane Party Committee, and Chairman of the Vientiane People's Council.
18:37 12/05/2026
Hanoi approves resolution guiding legal implementation mechanisms under 2026 Capital Law framework
Hanoi approves resolution guiding legal implementation mechanisms under 2026 Capital Law framework
On May 11, during its second session, the 17th Hanoi People's Council unanimously passed a resolution regulating several issues related to drafting and issuing legal normative documents to implement the Capital Law.
18:46 11/05/2026
Hanoi establishes Steering Committee on Waste Prevention and Control
Hanoi establishes Steering Committee on Waste Prevention and Control
Chairman of the Hanoi People's Committee Vu Dai Thang has signed Decision No. 2415/QD-UBND, dated May 11, 2026, establishing the Hanoi Steering Committee on Waste Prevention and Control.
18:41 11/05/2026