Hanoi accelerates metro construction and narrows barriers to ease traffic

2:52 PM, Fri February 27, 2026

On February 27, Nguyen Trong Dong, member of the Party Central Committee, Standing Vice Secretary of the Hanoi Party Committee and Head of the Steering Committee for Site Clearance of Investment Projects in Hanoi, inspected several metro station construction sites along the Kim Ma – Hanoi Station – Tran Hung Dao section.

Hanoi accelerates metro construction and narrows barriers to ease traffic- Ảnh 1.

Nguyen Trong Dong, Standing Vice Secretary of the Hanoi Party Committee, inspects the progress of the metro line connecting Kim Ma Street to Hanoi Railway Station.

On February 27, Nguyen Trong Dong, member of the Party Central Committee, Standing Vice Secretary of the Hanoi Party Committee and Head of the Steering Committee for Site Clearance of Investment Projects in Hanoi, inspected several metro station construction sites along the Kim Ma – Hanoi Railway Station – Tran Hung Dao section.

Reporting on project progress, Nguyen Cao Minh, Director of the Hanoi Urban Railway Management Board, said the pilot urban railway project from Nhon to Hanoi Station spans 12.5 kilometers, including 8.5 kilometers elevated and 4 kilometers underground, with eight elevated stations (S1–S8) and four underground stations (S9–S12).

Total investment exceeds VND34.8 trillion (US$1.3 billion), funded by ODA loans from four donors and counterpart capital from the city, with implementation from 2009 to 2027, with the elevated section from Nhon to Cau Giay has been operational since August 8, 2024, meeting quality and safety standards and receiving positive public response.

The underground portion includes four kilometers of tunnels, four underground stations and one emergency shaft. Construction progress has reached 76.3%, broadly meeting schedule targets.

Site clearance has been largely completed. Relocation of technical infrastructure has been conducted in parallel with construction due to limited space while maintaining traffic flow. As for tunnel and station, construction remain on schedule.

TBM1 completed tunneling on December 1, 2025 and is being dismantled at Station S12 – Tran Hung Dao. TBM2 is working on the S11–S12 section and is expected to finish in March 2026.

Construction progress at underground stations is as follows: the tunnel portal area is 89.01% complete, Station S9 is 50.09%, Station S10 is 72.27%, Station S11 is 67.76% and Station S12 is 75.60% complete.

Over 90% of the tunnel length has been completed using earth pressure balance TBM technology, ensuring quality and safety.

Hanoi accelerates metro construction and narrows barriers to ease traffic- Ảnh 2.

Standing Vice Secretary of the Hanoi Party Committee Nguyen Trong Dong listens to field reports.

As of February 10, 2026, disbursement exceeded VND25 trillion ($963 million), equivalent to 72.53% of total investment.

Nguyen Van Manh, Head of Contract Package CP03, said the management board coordinated with the Hanoi Department of Construction and relevant units to reduce construction barrier areas to ease traffic while ensuring safety and project progress.

At Station S9 – Kim Ma, fencing has been shortened by about 400 meters and narrowed by 0.5–1 meter, with additional reductions near 304 Kim Ma Street.

At the Lieu Giai – Kim Ma intersection, barriers were moved inward to create a temporary 3.5-meter-wide right-turn lane, easing congestion.

At the Kim Ma – Nui Truc intersection emergency shaft, fencing was reduced by about 10 meters and the temporary connecting road was widened from 6 meters to 12 meters to improve vehicle flow.

At Station S11 – Van Mieu on Temple of Literature Street, fencing was reduced by 100 meters, expanding roadway width from 7 meters to 9 meters and 10 meters of fencing at the Temple of Literature intersection was removed to improve visibility and traffic flow.

At Station S12 – Tran Hung Dao and the depot area, fencing was narrowed by 1–2 meters to widen the roadway and decorative panels were installed to enhance the urban landscape.

After inspecting the sites and reviewing progress, Standing Vice Secretary of the Hanoi Party Committee Nguyen Trong Dong emphasized that the Nhon – Hanoi Station metro line is Hanoi's first underground metro and a key project in the capital's sustainable urban development strategy.

He acknowledged the efforts of the Urban Railway Management Board and contractors in maintaining progress while ensuring traffic organization, safety and environmental hygiene in the dense inner city.

Hanoi accelerates metro construction and narrows barriers to ease traffic- Ảnh 3.

A construction site of the project.

Highlighting Hanoi's focus on addressing five major bottlenecks, including traffic congestion, Dong urged project managers and contractors to mobilize all resources to accelerate progress through a rolling construction approach.

He required scientific and coordinated construction methods, integrated underground technical infrastructure planning and adherence to standards to ensure timely and high-quality completion.

In particular, he stressed that construction barriers should be removed promptly upon completion of each section to restore road space and reduce localized congestion around worksites.

Hanoi vice chairwoman inspects election preparations in Hong Ha Ward ahead of voting day

16:56 03/03/2026

On March 3, at the Hong Ha Ward People's Committee, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha chaired an inspection meeting on preparations for the election of deputies to the 16th National Assembly and People's Councils for the 2026–2031 term in the ward.

Most views
Same category
Find by date
Hanoi vice chairwoman inspects election preparations in Hong Ha Ward ahead of voting day
Hanoi vice chairwoman inspects election preparations in Hong Ha Ward ahead of voting day
On March 3, at the Hong Ha Ward People's Committee, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha chaired an inspection meeting on preparations for the election of deputies to the 16th National Assembly and People's Councils for the 2026–2031 term in the ward.
16:56 03/03/2026
Hanoi leads nationwide in comprehensive preparation for upcoming elections
Hanoi leads nationwide in comprehensive preparation for upcoming elections
At the February review meeting and the launch of tasks for March 2026, Phung Thi Hong Ha, Deputy Secretary of the Hanoi Party Committee and Chairwoman of the Hanoi People's Council, said March and the second quarter of 2026 would be a decisive period for finalizing materials for the fifth conference of the Hanoi Party Committee and preparing for the first session and the mid-year regular session of the city People's Council.
16:51 03/03/2026
Officials must elevate capacity and mindset to meet unprecedented responsibilities ahead
Officials must elevate capacity and mindset to meet unprecedented responsibilities ahead
Concluding the February work review meeting and launching tasks for March 2026, Politburo member and Secretary of the Hanoi Party Committee Nguyen Duy Ngoc said the capital achieved many positive results in February.
16:50 03/03/2026
Hanoi Fatherland Front strengthens oversight to ensure democratic and lawful election process
Hanoi Fatherland Front strengthens oversight to ensure democratic and lawful election process
Speaking at the February work review meeting and outlining key tasks for March 2026, Bui Huyen Mai, member of the Hanoi Party Committee's Standing Board and Chairwoman of the Vietnam Fatherland Front Committee of Hanoi, highlighted four major groups of tasks for the coming month.
16:31 03/03/2026
Hanoi council chairwoman inspects election preparations in O Dien Commune
Hanoi council chairwoman inspects election preparations in O Dien Commune
On March 1, Inspection Team No. 3 of the Hanoi Party Standing Committee reviewed preparations for the election of deputies to the 16th National Assembly and People's Councils for the 2026–2031 term in O Dien Commune.
16:23 01/03/2026
Cheo Tau festival recognized as national intangible cultural heritage
Cheo Tau festival recognized as national intangible cultural heritage
On March 1, during the traditional festival at Mieu Voi Phuc Communal House and Lang Van Son in O Dien Commune, authorities held a ceremony to announce the official recognition of the Cheo Tau Festival of Tong Goi as a National Intangible Cultural Heritage and to award heritage status certificates to Phan Long and Thuy Hoi communal houses.
16:09 01/03/2026
Other news
Hanoi partners with international experts to strengthen public sector strategic leadership
Hanoi partners with international experts to strengthen public sector strategic leadership
As part of a working visit to the Ho Chi Minh National Academy of Politics, a delegation of experts from the Australia and New Zealand School of Government on the morning of March 3 visited and worked with the Le Hong Phong Training School for Officials of Hanoi and held a dialogue titled "Strengthening Strategic Leadership Skills in the Public Sector."
16:42 03/03/2026
Hanoi raises legal awareness on religion and elections among Protestant community
Hanoi raises legal awareness on religion and elections among Protestant community
The Hanoi Department of Ethnic and Religious Affairs on the afternoon of March 2 held a conference to disseminate and promote legal knowledge on religion and belief, as well as laws related to the election of deputies to the National Assembly and People's Councils at all levels for the Protestant community in 2026.
16:42 02/03/2026
Hanoi launches emulation campaign to celebrate major anniversaries in 2026
Hanoi launches emulation campaign to celebrate major anniversaries in 2026
Standing Vice Chairman of the Hanoi People's Committee Duong Duc Tuan has signed and issued Plan No. 80/KH-UBND dated March 2, 2026 on launching emulation movements to celebrate major national anniversaries in 2026.
16:39 02/03/2026
Hanoi promotes heritage preservation with sustainable development
Hanoi promotes heritage preservation with sustainable development
In response to voters' questions regarding the project to preserve, restore and promote the value of Duong Lam Ancient Village in connection with the construction of the Tich River Park, Chairman of the Hanoi People's Committee Vu Dai Thang affirmed that this is a matter of special importance in the capital's development planning.
16:26 02/03/2026
Chairman of the Hanoi People's Committee Vu Dai Thang meets voters ahead of upcoming election
Chairman of the Hanoi People's Committee Vu Dai Thang meets voters ahead of upcoming election
Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang, together with candidates for the 17th Hanoi People's Council for the 2026-2031 term from Constituency No. 14, on the morning of March 2, met with voters to present their action programs and conduct election campaigning.
16:18 02/03/2026
Hanoi announces new intangible cultural heritage
Hanoi announces new intangible cultural heritage
During the traditional festival of Mieu Voi Phuc Communal House and Van Son Mausoleum On the morning of March 1, the 13th day of the first lunar month in the Year of the Horse, the Party Committee, People's Council, People's Committee and Fatherland Front Committee of O Dien Commune held a ceremony to announce the inscription of the Tong Goi Cheo Tau Singing Festival on the National List of Intangible Cultural Heritage and to present heritage ranking certificates to Phan Long Communal House and Thuy Hoi Communal House.
16:23 01/03/2026
Hanoi promotes efforts against drug use
Hanoi promotes efforts against drug use
Standing Vice Chairman of the Hanoi People's Committee Duong Duc Tuan has signed and issued Plan No. 76/KH-UBND dated February 28, 2026 to implement Project 4 titled "Enhancing the effectiveness of grassroots drug prevention and control" under the National Target Program on Drug Prevention and Control through 2030 in Hanoi.
16:35 28/02/2026
Hanoi ranks historical and cultural relics in the city
Hanoi ranks historical and cultural relics in the city
Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha has signed and issued Decision No. 882/QD-UBND dated February 27, 2026 on the ranking of historical and cultural relics and scenic sites across Hanoi.
16:33 27/02/2026