Hanoi wants to complete renovation and cleanup along To Lich River by August 30

4:57 PM, Mon July 07, 2025

Deputy Chairman Nguyen Trong Dong has urged local wards to enhance public communication efforts, encouraging residents to maintain sanitation and dispose of waste in designated areas.

Hanoi wants to complete renovation and cleanup along To Lich River by August 30- Ảnh 1.

General view of the meeting.

The Hanoi People's Committee on July 7 co-chaired a working session to review the progress of environmental sanitation and landscape renovation along both banks of the To Lich River, and the plan to replenish water for the river.

According to Director of the Hanoi Department of Construction Nguyen Phi Thuong, Phase I of the riverbed dredging project – stretching from Hoang Quoc Viet Street to Khuong Dinh Bridge – has been completed.

This section covers about 7 kilometers, with approximately 49,914 cubic meters of mud removed.

Phase II, from Khuong Dinh Bridge to Long Quang Pagoda, is expected to be completed in August 2025.

This segment is 5 kilometers long with an estimated 11,800 cubic meters of sludge to be removed.

Regarding the connection of 63 remaining sewage outlets along the To Lich River, from Hoang Quoc Viet to the To Lich floodgate, 19 have been connected and work is underway on 42 more.

The goal is to finish construction on all outlets by the end of July 2025 so that surface restoration and beautification can be completed in August.

As for the section from the floodgate to the river's confluence with the Nhue River, about 10 outlets remain on the right bank of the To Lich, and around 63 on the lower left bank of the Kim Nguu River.

The Project Management Board is currently researching a separate project for this area, which will be integrated into the Yen Xa wastewater treatment project.

The Department of Construction has also instructed the city's Technical Infrastructure Management Center and contractors to regularly maintain landscaping along Lang Street and both banks of the To Lich River.

This includes caring for ornamental trees, shrubbery, and grass in accordance with city regulations to ensure cleanliness and aesthetics.

For water replenishment, the city will initially use treated water from the West Lake Wastewater Treatment Plant.

In the long term, the Department of Construction is working with consultants to explore options for drawing water from the Red River.

According to Deputy Chairmen Nguyen Trong Dong and Duong Duc Tuan, all wards along the To Lich River to complete sidewalk paving, railing installation, and tree planting on both banks no later than August 30.

Construction sites must be cleaned and the surface restored immediately upon the completion of work at each outlet.

Hanoi wants to complete renovation and cleanup along To Lich River by August 30- Ảnh 2.

Construction department director Nguyen Phi Thuong speaks at the meeting.

Dong also urged local wards to enhance public communication efforts, encouraging residents to maintain sanitation and dispose of waste in designated areas.

The Departments of Agriculture and Environment were tasked with promptly installing waste bins along both banks of the river to help maintain cleanliness.

In the immediate future, and in line with national leaders' directives to revive the To Lich River, special attention must be paid to the plan to supplement the river's water flow.

If water from West Lake is used, its volume and quality must be carefully studied to avoid altering the hydrological or ecological balance of the river.

In addition, cooperation with the To Lich floodgate system at the downstream area near the Yen Xa wastewater treatment plant is required to create additional water sources for the river.

The larger proposal of using water from the Red River to replenish both West Lake and the To Lich River must be closely monitored.

All aspects of the project, including total investment, cost components, operating and maintenance expenses, must be clearly assessed.

Environmental conditions in West Lake must be strictly controlled to avoid any negative ecological impacts when new water sources are introduced.

Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region

15:18 21/05/2026

On May 21, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha inspected the construction site and worked with departments, agencies and related units on the implementation progress of the second campus project of Hanoi Heart Hospital in Xuan Dinh Ward.

Most views
Same category
Find by date
Hanoi Chairman calls for waste treatment linked to green urban recovery
Hanoi Chairman calls for waste treatment linked to green urban recovery
Chairman of the Hanoi People's Committee Vu Dai Thang on May 20 inspected the Xuan Son solid waste treatment complex and visited the Seraphin waste-to-energy plant operated by AMACCAO Group, where city officials reviewed the overall status of solid waste treatment across Hanoi.
15:15 20/05/2026
Hanoi urges faster progress on Yen Ky cemetery park project
Hanoi urges faster progress on Yen Ky cemetery park project
A Hanoi delegation led by Vu Dai Thang, member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on May 20 inspected the Vinh Hang Cemetery in Vat Lai Commune and reviewed reports on planning, investment, and management of the Vinh Hang and Yen Ky cemetery projects, along with other cemeteries across the city.
15:14 20/05/2026
Hanoi breaks ground on Phu Ha industrial park, targets green industrial model
Hanoi breaks ground on Phu Ha industrial park, targets green industrial model
Hanoi authorities on the morning of May 19 held the groundbreaking ceremony for the Phu Ha Industrial Park project, covering nearly 175 hectares with a total investment of more than VND2.9 trillion (US$111.5 million). The project will be developed in Chuong Duong and Thuong Phuc communes.
15:14 19/05/2026
Hanoi signs MoU on electric motorcycle battery swap station project
Hanoi signs MoU on electric motorcycle battery swap station project
Truong Viet Dung, Vice Chairman of the Hanoi People's Committee, on the morning of May 19, presided over the signing ceremony for a memorandum of understanding among the Hanoi Department of Construction, LG Energy Solution of South Korea, and Honda Motor of Japan on a project to install battery swap stations for electric motorcycles in Hanoi.
14:29 19/05/2026
Hanoi eyes western growth boost through cultural village transfer
Hanoi eyes western growth boost through cultural village transfer
A Hanoi delegation led by Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on May 18, conducted a field inspection and held a working session with the Ministry of Culture, Sports and Tourism and related agencies regarding the transfer and handover of the Vietnam National Village for Ethnic Culture and Tourism.
14:36 18/05/2026
Hanoi moves ahead with plan to take over Ba Vi National Park
Hanoi moves ahead with plan to take over Ba Vi National Park
Vu Dai Thang, member of the Party Central Committee, deputy secretary of the Hanoi Party Committee and chairman of the Hanoi People’s Committee, led a city delegation on May 18 to inspect preparations for Ba Vi National Park’s handover to the city and its subsequent management.
14:28 18/05/2026
Other news
Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region
Hanoi accelerates construction progress for major second cardiovascular hospital project serving northern region
On May 21, Vice Chairwoman of the Hanoi People's Committee Vu Thu Ha inspected the construction site and worked with departments, agencies and related units on the implementation progress of the second campus project of Hanoi Heart Hospital in Xuan Dinh Ward.
15:18 21/05/2026
Hanoi strengthens strategic partnership with Saint Petersburg through expanding legislative cooperation initiatives
Hanoi strengthens strategic partnership with Saint Petersburg through expanding legislative cooperation initiatives
As part of Hanoi’s 2026 foreign affairs agenda, a Hanoi delegation visited and worked in Saint Petersburg, Russia, from May 18 to May 20 at the invitation of the Legislative Assembly and the External Relations Committee of Saint Petersburg.
15:17 21/05/2026
Hanoi launches smart eco-industrial park advancing northern innovation and manufacturing growth ambitions
Hanoi launches smart eco-industrial park advancing northern innovation and manufacturing growth ambitions
On May 20, the Hanoi People's Committee and the Vietnam Construction and Import-Export Joint Stock Corporation (VINACONEX) broke ground on the Dong Anh Industrial Park infrastructure construction and business investment project.
15:18 20/05/2026
Hanoi steps up digital transformation and innovation in culture
Hanoi steps up digital transformation and innovation in culture
The Hanoi People's Committee Office has issued Notice No. 404/TB-VP, dated May 19, 2026, outlining conclusions by Vice Chairman of the Hanoi People's Committee Truong Viet Dung at a meeting reviewing digital transformation, science and technology, and innovation in the cultural sector.
15:16 19/05/2026
Hanoi launches major waste-to-energy plant advancing sustainable urban environmental transformation goals
Hanoi launches major waste-to-energy plant advancing sustainable urban environmental transformation goals
The Nui Thoong High-Tech Environmental Treatment and Waste-to-Energy Plant project is the first high-tech waste-to-energy plant project in southwestern Hanoi and is expected to become a strategic component in the capital's waste-to-energy development network.
15:10 19/05/2026
Hanoi honors veteran Party members for revolutionary dedication
Hanoi honors veteran Party members for revolutionary dedication
On the occasion of the 136th anniversary of President Ho Chi Minh's birth (May 19, 1890 - May 19, 2026), the Hanoi Party Committee on May 19 organized a ceremony to award 80-year, 75-year and 70-year Party membership badges in the May 19, 2026 recognition round.
15:10 19/05/2026
New highway corridor reshapes southern Hanoi with ambitious urban redevelopment vision
New highway corridor reshapes southern Hanoi with ambitious urban redevelopment vision
The project carries special significance for the city's strategy to develop urban space, strengthen regional connectivity and modernize southern Hanoi's infrastructure system in the new development phase.
15:09 19/05/2026
Hanoi strengthens strategic infrastructure cooperation with major Chinese construction corporation leaders
Hanoi strengthens strategic infrastructure cooperation with major Chinese construction corporation leaders
On May 18, Politburo member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang hosted a working session with Pacific Construction Group of China.
15:10 18/05/2026