Hanoi Party Secretary urges progress on key projects, better living standards

10:39 PM, Sat April 18, 2026

Politburo Member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang inspected several key projects in Hanoi on April 18, including Ring Road 1 (Hoang Cau–Voi Phuc section), a drainage route linking DT4 Road in the Tay Ho Tay urban area to Hoang Quoc Viet Street, Yen Nghia 1 regulating lake, and La Khe Canal.

Bí thư Thành ủy Trần Đức Thắng kiểm tra thực địa Hồ điều hòa Yên Nghĩa 1

Hanoi Party Secretary Tran Duc Thang inspects Yen Nghia 1 regulating lake.

Joining the delegation were Party Central Committee Member, Standing Deputy Secretary of the Hanoi Party Committee Nguyen Trong Dong; members of the Standing Committee of the Hanoi Party Committee, including Chairman of the Inspection Commission Do Anh Tuan, Head of the Organization Commission Ha Minh Hai, Standing Vice Chairman of the Hanoi People's Committee Duong Duc Tuan, along with representatives of relevant departments, agencies, and local authorities.

Hanoi Party Secretary urges progress on key projects, better living standards- Ảnh 2.

Hanoi Party Secretary Tran Duc Thang inspects the progress of the Ring Road 1 project (Hoang Cau – Voi Phuc section)

The Ring Road 1 project (Hoang Cau – Voi Phuc section) is a Group A project with a total investment of more than VND7,210 billion (US$288 million). Construction began in June 2020 and, after multiple adjustments, is scheduled for completion in 2026. To date, site clearance covering 153,341 square meters, affecting 1,983 households in O Cho Dua, Lang, and Giang Vo wards, has been completed and handed over for construction.

The construction package for the road and two overpasses at the Lang Ha – Giang Vo intersection began on January 9, 2026. Contractors have completed demolition, site clearance, waste removal, and relocation of trees along the entire route. 

Construction progress has reached about 50 percent. Drainage systems, technical ducts, roadbeds, and relocation of power, water, and telecommunications infrastructure are being carried out in phases, including during holidays. Asphalt paving from Km2+500 to Km2+816 has been completed, and the technical route was opened to traffic before January 15, 2026.

Work on the two overpasses is also accelerating. The Lang Ha overpass has completed all six piers, reaching 50 percent of the total volume. The Nguyen Chi Thanh overpass has reached about 20 percent and is preparing for main span construction starting in June 2026. The project has fully disbursed its 2025 capital plan, reaching 100 percent, while nearly 14.5 percent of the VND600 billion (US$24 million) allocated for 2026 has been disbursed.

Hanoi Party Secretary urges progress on key projects, better living standards- Ảnh 3.

Hanoi Party Secretary Tran Duc Thang inspects the DT4 drainage route from Tay Ho Tay urban area to Hoang Quoc Viet Street.

The DT4 drainage route is an emergency project managed by the city's Technical Infrastructure Management Center. It includes the installation of a 530.8-meter D1000 pipeline and the construction of a 530-meter open canal combined with box culverts. The pipeline section that did not require site clearance was completed on April 15, 2026, 15 days ahead of the scheduled deadline.

Hanoi Party Secretary urges progress on key projects, better living standards- Ảnh 4.

The DT4 drainage route is being urgently constructed

The open canal section requires site clearance of nearly 21,820 square meters. On February 26, 2026, Nghia Do Ward handed over 15,800 square meters of agricultural land for construction. Work on the canal has reached about 65 percent completion. The investor and contractor are mobilizing maximum manpower and equipment, aiming to open the technical route to traffic before April 30, 2026, and complete railings, sidewalks, and landscaping before May 15, 2026.

Of the 40 items under three emergency orders, 36 are expected to be completed by April 25, 2026, to allow trial operation of the pumping system and technical connection. The remaining four items, including the DT4 canal, are scheduled for completion by April 30, 2026.

Hanoi Party Secretary urges progress on key projects, better living standards- Ảnh 5.

Hanoi Party Secretary Tran Duc Thang inspects Yen Nghia 1 regulating lake project

The Yen Nghia 1 regulating lake project in An Khanh Commune is being implemented under an emergency order, with a total investment of VND854.4 billion (US$34.2 million). The lake covers about 20 hectares and has a storage capacity of 0.5 million cubic meters. Site clearance for 23.5 hectares has been fully completed. Medium- and low-voltage power systems are being connected and are expected to be completed by April 28, 2026. 

Since late January 2026, construction has been carried out simultaneously at 15 work fronts, maintaining rapid progress and gradually forming the lake basin and embankment structures.

Hanoi Party Secretary urges progress on key projects, better living standards- Ảnh 6.

The Yen Nghia 1 regulating lake project is being carried out simultaneously at 15 work fronts

The project to improve the western drainage system of the city, focusing on Yen Nghia pumping station and La Khe Canal, has total investment of more than VND4,722 billion (US$189 million). The pumping station hub, including seven packages, has been completed and put into operation. Current focus is on 12 packages along La Khe Canal.

Site clearance has been largely completed in An Khanh Commune, Ha Dong Ward, and Duong Noi Ward. However, some households still need to partially demolish structures, and several power and water infrastructure points have not yet been relocated, affecting progress on roads along the canal.

All 12 canal packages have been launched, reaching 86 percent completion. Two packages are finished, four have largely completed dredging, two are accelerating, and two have had contracts terminated due to contractor underperformance. The project management board has proposed applying emergency procedures to appoint new contractors for the remaining work, focusing on prestressed concrete sheet piles and dredging.

The target is to complete canal dredging by April 30, 2026, finish bottom support beams by June 30, and complete remaining items by September 30. At the same time, flood prevention measures are being prepared to ensure effective drainage to Yen Nghia pumping station during the 2026 rainy season.

At the Ring Road 1 site, Tran Duc Thang stressed that the project is a backbone route that will ease congestion in the city center, open new development space, and connect key areas of the capital. Each day of delay means continued congestion, pollution, longer travel times, and a lower quality of life for residents.

He directed project management units, departments, and local authorities to fully review construction processes, identify bottlenecks, and set clear solutions and deadlines. The roadbed must be completed before September 2, 2026, and both overpasses finished before December 31, 2026.

He also required investors and contractors to commit in writing to timelines for key items, implement catch-up construction plans, and ensure safety and quality. The city will strengthen inspections and take firm action against units that fail to meet requirements or delay progress.

At the DT4 drainage project, Tran Duc Thang emphasized its importance for Tay Ho Tay and surrounding areas, where population density and development are increasing rapidly. Delays could lead to flooding that disrupts daily life and business activities. He required completion of the canal section by April 30, 2026, and sidewalks by May 15, 2026.

He also called for close coordination among agencies, especially utilities managing electricity, water, and telecommunications, to avoid delays caused by administrative procedures or a lack of coordination.

At Yen Nghia 1 regulating lake, he stressed that the project is not only a drainage solution but also a "green lung" and community space for tens of thousands of residents. He directed agencies to develop synchronized planning for surrounding infrastructure, including roads, greenery, lighting, and public spaces. The lake basin must be completed by April 30, 2026, and surrounding landscaping by June 30, 2026.

At La Khe Canal, he noted that the canal is both a key drainage route and a visible reflection of the local living environment. Its renovation is therefore both a technical and political task, closely linked to public trust in local authorities.

He requested Ha Dong Ward and the project management board to report on pollution sources, illegal discharges, encroachments, and violations, and to develop a clear plan for comprehensive handling. Violations must be strictly addressed.

Construction packages for canal works must be completed before April 30, 2026, to ensure stable drainage to Yen Nghia pumping station, with landscape items completed before June 30, 2026.

He emphasized that the renovation of La Khe Canal should create a clean, safe green corridor connected to surrounding roads and residential areas, helping raise property values and improve living conditions. Project timelines must be transparent and closely monitored, allowing public participation and oversight.

Hanoi advances digital transformation to strengthen Party organizations and governance capacity citywide

15:36 29/04/2026

On April 29, a delegation from the Central Party Committee's Organization Commission conducted a survey on Party building and rectification, efforts to strengthen the political system, and measures to improve the quality of Party organizations and members within the Hanoi Party Committee.

Most views
Same category
Find by date
Hanoi steps up cooperation with Japanese localities
Hanoi steps up cooperation with Japanese localities
As part of its working visit to Japan, Hanoi's delegation, led by Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, carried out a series of activities in Osaka and Tokyo on April 26-27, focusing on expanding cooperation with Japanese local governments in innovation, science and technology, and digital transformation, while also strengthening ties with the Vietnamese intellectual and expert community in Japan.
15:19 26/04/2026
Revised Capital Law grants Hanoi powers and drives breakthrough development opportunities forward
Revised Capital Law grants Hanoi powers and drives breakthrough development opportunities forward
With an overwhelming majority of votes, the 16th National Assembly has passed the revised Capital Law, granting more than 190 specific and outstanding powers to the Hanoi city government.
15:38 23/04/2026
Hanoi welcomes South Korea's Lotte Group to deepen urban development cooperation
Hanoi welcomes South Korea's Lotte Group to deepen urban development cooperation
Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on April 22, received Shin Dong Bin, Chairman of Lotte Group, during a courtesy visit and discussion on issues of mutual interest.
18:29 22/04/2026
Hanoi targets bottlenecks to fast-track key projects
Hanoi targets bottlenecks to fast-track key projects
Politburo Member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang on the afternoon of April 19 chaired a working session on the progress of major flood prevention and drainage projects and key transport projects across Hanoi.
18:24 19/04/2026
Binh Da festival 2026 opens with impressive ceremony
Binh Da festival 2026 opens with impressive ceremony
The Party Committee, the People's Council, the People's Committee, and the Vietnam Fatherland Front Committee of Binh Minh Commune on the evening of April 19 solemnly held the opening ceremony of the 2026 Binh Da Festival, Spring of the Binh Ngo Year at Dinh Noi in Binh Da, Binh Minh Commune. The festival officially runs from April 19 to 22, 2026, corresponding to the 3rd through the 6th days of the third lunar month of the Binh Ngo Year 2026.
18:24 19/04/2026
Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects
Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects
Politburo Member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang on the afternoon of April 19 continued his on-site inspections of major infrastructure projects in the capital, including the Me So Bridge-Component Project 3 of the Ring Road 4 – Hanoi Capital Region Investment Project; the Ngoc Hoi Bridge and its approach roads; and the Ring Road 2.5 project.
17:55 19/04/2026
Other news
Hanoi advances digital transformation to strengthen Party organizations and governance capacity citywide
Hanoi advances digital transformation to strengthen Party organizations and governance capacity citywide
On April 29, a delegation from the Central Party Committee's Organization Commission conducted a survey on Party building and rectification, efforts to strengthen the political system, and measures to improve the quality of Party organizations and members within the Hanoi Party Committee.
15:36 29/04/2026
Hanoi breaks ground on expanded waste-to-energy plant
Hanoi breaks ground on expanded waste-to-energy plant
On April 29, the Hanoi People's Committee, in coordination with Hanoi Thien Y Environmental Energy Joint Stock Company, held the groundbreaking ceremony for the expansion of the Soc Son Waste to Energy Plant at the Nam Son Solid Waste Treatment Complex in Trung Gia Commune.
15:31 29/04/2026
Hanoi to host 2nd Thang Long - Hanoi festival celebrating heritage and creativity
Hanoi to host 2nd Thang Long - Hanoi festival celebrating heritage and creativity
Chairman of the Hanoi People's Committee Vu Dai Thang has signed Plan No. 173/KH-UBND dated April 28, 2026 on organizing the "Second Thang Long Hanoi Festival 2026."
15:31 28/04/2026
Hanoi and Tokyo expand technology partnership to advance sustainable urban development goals
Hanoi and Tokyo expand technology partnership to advance sustainable urban development goals
On April 28, as part of an official visit to Japan, a high level delegation of Hanoi met with Tokyo Governor Koike Yuriko, attended the SusHi Tech Tokyo 2026 high tech exhibition, joined the Global Network of Sustainable Cities Summit (G-NETS) 2026 and held a bilateral meeting with representatives of the Asian Development Bank (ADB).
15:29 28/04/2026
Hanoi tests 15 anti-flooding pumping stations ahead of rainy season
Hanoi tests 15 anti-flooding pumping stations ahead of rainy season
On April 28, the Hanoi Technical Infrastructure Management Center under the Hanoi Department of Construction will coordinate with relevant units to simultaneously activate and test 15 pumping stations for lake water regulation, aiming to prevent flooding during the rainy season.
15:21 28/04/2026
Hanoi ensures seamless, integrated and efficient citywide public services
Hanoi ensures seamless, integrated and efficient citywide public services
Vice Chairman of the Hanoi People's Committee Truong Viet Dung has signed Official Letter No. 1747/UBND-NC dated April 25, 2026 on implementing administrative procedures and online public services in a synchronized, integrated, efficient and uninterrupted manner across Hanoi.
15:31 25/04/2026
Hanoi accelerates public investment disbursement as driver for double digit economic growth
Hanoi accelerates public investment disbursement as driver for double digit economic growth
On April 24, at the national conference on accelerating allocation and disbursement of public investment capital in 2026, Party Central Committee Member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang delivered remarks at the Hanoi People's Committee site.
15:29 24/04/2026
National Flags to be flown for April 30 and May 1 holidays
National Flags to be flown for April 30 and May 1 holidays
The Hanoi People's Committee has issued Notice No. 434/TB-UBND dated April 24, 2026 regarding the flying of the national flag.
15:19 24/04/2026