EVNHANOI accelerates key power grid projects to strengthen capital's electricity supply

9:05 PM, Fri March 20, 2026

Closely following its 2026 production, business and investment plan, the Hanoi Power Corporation (EVNHANOI) is actively implementing a series of key power grid projects from the beginning of the year to enhance supply capacity and meet the capital's socio-economic development needs.

EVNHANOI accelerates key power grid projects to strengthen capital's electricity supply- Ảnh 1.

EVNHANOI has held many meetings to review and ensure its sufficient operations.

Closely following its 2026 production, business and investment plan, the Hanoi Power Corporation (EVNHANOI) is actively implementing a series of key power grid projects from the beginning of the year to enhance supply capacity and meet the capital's socio-economic development needs.

At construction sites, work has been progressing rapidly since the early days of the year, with contractors mobilizing manpower, machinery and equipment to carry out multiple project components simultaneously.

At several 110kV substations and transmission line projects, foundation construction, steel structure installation and cable connections are being implemented according to schedule.

Under the plan, EVNHANOI will continue investing in 220kV and 110kV grid infrastructure to improve transmission capacity and ensure safe system operation.

The corporation is focusing on new projects such as the Long Bien 2 220kV substation, Soc Son 2 220kV substation and Chuong My 220kV substation, along with synchronized transmission lines, helping strengthen power supply in areas with rapidly growing demand.

EVNHANOI accelerates key power grid projects to strengthen capital's electricity supply- Ảnh 2.

The Hai Boi power station in Dong Anh Commune.

In addition to new construction, EVNHANOI is upgrading existing substations to meet increasing load demands, including capacity expansion at Phu Nghia 110kV substation and Hai Boi 110kV substation.

Project management boards and contractors are intensifying efforts by deploying more resources and equipment to implement construction, steel assembly and installation tasks.

Many projects are progressing in line with plans to be put into operation soon, meeting the capital's rising electricity demand.

EVNHANOI regularly conducts site inspections and coordinates with consultants and contractors to promptly resolve challenges during implementation.

At the same time, strict attention is paid to occupational safety, equipment quality control and construction progress management to ensure projects are completed on schedule.

EVNHANOI accelerates key power grid projects to strengthen capital's electricity supply- Ảnh 3.

The installation of power lines in Phu Cat Commune.

To accelerate progress, the corporation has strengthened coordination with departments, sectors and local authorities in investment preparation, site clearance and legal procedures. Many management solutions and digital technologies were applied to monitor progress and ensure quality across projects.

Accelerating power grid investment from the beginning of the year is identified as a key task for EVNHANOI in 2026. Once completed, these projects will enhance electricity supply capacity, improve system stability and meet growing demand in new urban areas, industrial zones and key economic regions of Hanoi.

Hanoi chairman Vu Dai Thang orders land clearance completion by Q2, 2026

17:16 19/04/2026

On April 19, Party Central Committee Member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang, along with a city delegation, conducted an on-site inspection of the progress of the project to upgrade and expand Road 70 and the project to renovate and expand National Highway 21B.

Most views
Same category
Find by date
Hanoi chairman Vu Dai Thang orders land clearance completion by Q2, 2026
Hanoi chairman Vu Dai Thang orders land clearance completion by Q2, 2026
On April 19, Party Central Committee Member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang, along with a city delegation, conducted an on-site inspection of the progress of the project to upgrade and expand Road 70 and the project to renovate and expand National Highway 21B.
17:16 19/04/2026
Hanoi leads in deep dialogue creating momentum for SME development nationwide
Hanoi leads in deep dialogue creating momentum for SME development nationwide
The 2026 dialogue conference with small and medium sized enterprises in Hanoi is a highly meaningful event, demonstrating a practical, specific and effective approach in supporting businesses, contributing to the implementation of Resolution 68 of the Politburo on private sector development.
23:04 16/04/2026
Hanoi Chairman Vu Dai Thang engages SMEs in dialogue to boost growth
Hanoi Chairman Vu Dai Thang engages SMEs in dialogue to boost growth
On April 16, Party Central Committee member, Vice Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang chaired a dialogue conference with small and medium sized enterprises across the city in 2026.
23:02 16/04/2026
Hanoi ensures all administrative procedures resolved at commune level for citizens
Hanoi ensures all administrative procedures resolved at commune level for citizens
On April 16, Party Central Committee member, Deputy Secretary of the Hanoi Party Committee and Chairman of the Hanoi People's Committee Vu Dai Thang chaired a meeting with leaders of departments, agencies and commune and ward authorities on administrative reform, administrative procedure control, implementation of procedures and decentralization and delegation across the city.
16:33 16/04/2026
Hanoi tax authority strengthens direct support addressing enterprise tax challenges effectively
Hanoi tax authority strengthens direct support addressing enterprise tax challenges effectively
On April 16, at the 2026 dialogue conference with small- and medium-sized enterprises in the city, Vu Manh Cuong, Head of Hanoi Tax Department, addressed questions from businesses on various tax related issues.
16:22 16/04/2026
Digital transformation in elected bodies enhances governance capacity and public service quality
Digital transformation in elected bodies enhances governance capacity and public service quality
On April 16, Vice Secretary of the Hanoi Party Committee and Chairwoman of the Hanoi People's Council Phung Thi Hong Ha, who also serves as Deputy Head of the Hanoi National Assembly Delegation and Head of the Steering Committee for science, technology, innovation, and digital transformation of the National Assembly Delegation and People's Council of Hanoi, chaired a meeting of the Steering Committee.
15:47 16/04/2026
Other news
Hanoi issues investment regulations for Hanoi Venture Capital Fund
Hanoi issues investment regulations for Hanoi Venture Capital Fund
Vice Chairman of the Hanoi People's Committee Truong Viet Dung has signed Decision No. 2147/QD-UBND, dated April 22, 2026, promulgating the investment regulations for the Hanoi Venture Capital Fund.
18:31 22/04/2026
Hanoi welcomes South Korea's Lotte Group to deepen urban development cooperation
Hanoi welcomes South Korea's Lotte Group to deepen urban development cooperation
Vu Dai Thang, Member of the Party Central Committee, Deputy Secretary of the Hanoi Party Committee, and Chairman of the Hanoi People's Committee, on April 22, received Shin Dong Bin, Chairman of Lotte Group, during a courtesy visit and discussion on issues of mutual interest.
18:29 22/04/2026
Hanoi launches 3rd contest to seek ideas and solutions for administrative reform
Hanoi launches 3rd contest to seek ideas and solutions for administrative reform
Vice Chairman of the Hanoi People's Committee Truong Viet Dung has signed and issued Plan No. 165/KH-UBND, dated April 21, 2026, on organizing the third contest to seek ideas and solutions for administrative reform across Hanoi in 2026.
18:26 21/04/2026
Hanoi sets plan for One Commune One Product program in 2026
Hanoi sets plan for One Commune One Product program in 2026
Vice Chairman of the Hanoi People's Committee Nguyen Xuan Luu has signed and issued Plan No. 163/KH-UBND, dated April 21, 2026, on the implementation of the One Commune One Product Program, or OCOP Program, in Hanoi in 2026.
18:25 21/04/2026
Hanoi promotes development of rural industries
Hanoi promotes development of rural industries
Vice Chairman of the Hanoi People’s Committee Nguyen Xuan Luu has signed and issued Plan No. 161/KH-UBND dated April 20, 2026, on the development of rural industries in Hanoi in 2026.
17:54 20/04/2026
Hanoi targets bottlenecks to fast-track key projects
Hanoi targets bottlenecks to fast-track key projects
Politburo Member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang on the afternoon of April 19 chaired a working session on the progress of major flood prevention and drainage projects and key transport projects across Hanoi.
18:24 19/04/2026
Binh Da festival 2026 opens with impressive ceremony
Binh Da festival 2026 opens with impressive ceremony
The Party Committee, the People's Council, the People's Committee, and the Vietnam Fatherland Front Committee of Binh Minh Commune on the evening of April 19 solemnly held the opening ceremony of the 2026 Binh Da Festival, Spring of the Binh Ngo Year at Dinh Noi in Binh Da, Binh Minh Commune. The festival officially runs from April 19 to 22, 2026, corresponding to the 3rd through the 6th days of the third lunar month of the Binh Ngo Year 2026.
18:24 19/04/2026
Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects
Hanoi Party Chief Tran Duc Thang continues on-site inspections of key capital projects
Politburo Member, Secretary of the Hanoi Party Committee and Head of the Hanoi National Assembly Delegation Tran Duc Thang on the afternoon of April 19 continued his on-site inspections of major infrastructure projects in the capital, including the Me So Bridge-Component Project 3 of the Ring Road 4 – Hanoi Capital Region Investment Project; the Ngoc Hoi Bridge and its approach roads; and the Ring Road 2.5 project.
17:55 19/04/2026