Ground broken for the construction of flyover at Hoang Quoc Viet - Nguyen Van Huyen intersection (18:10 09/10/2019)
The event saw the attendance of member of the Party Central Committee, Chairman of the Hanoi People’s Committee Nguyen Duc Chung; Vice Chairman of the National Steering Committee for Traffic Safety Khuat Viet Hung; Head of the Hanoi Party Committee’s Inspection Commission Hoang Trong Quyet; Head of the Municipal Party Committee’s Mass Mobilization Commission Nguyen Thi Tuyen; and Vice Chairman of the Municipal People’s Committee Nguyen The Hung.
The flyover has a total investment of VND560 billion (US$24.08 million) from the city’s budget. It measures 278m long and 16m wide.
The construction of the flyover is scheduled for completion in 285 days.
Vice Chairman of the Hanoi People’s Committee Nguyen The Hung speaks at the ceremony.
Speaking at the ceremony, Vice Chairman of the Hanoi People’s Committee Nguyen The Hung said that the flyover aims to handle the narrow section on Nguyen Van Huyen Street, thereby increasing traffic capacity, reducing congestion, and facilitating vehicles moving between the Belt Roads No.2 and No.3.
It also contributes to improving the transportation network as well as promoting socio-economic development in the district of Cau Giay, Tay Ho and North Tu Liem.
To carry out the project as scheduled, Hung requested Cau Giay District to speed up land clearance to soon hand over the ground to the construction unit.
He also asked construction contractors and relevant units to closely work with each other to implement the project as stipulated by law, and ensure the progress, quality, labor safety and environment during the construction.
• On the same day, a road connecting Hoang Quoc Viet Street with the Tay Ho Tay Urban Area was opened to traffic.